BRITISH COL UMBIA UTILITIES COM MISSION ORDER NUMBER G -59-06 SIXTH FLOOR, 900 HOWE STREET, BOX 250 TELEPHONE: (604) 660-4700 VANCOUVER, B.C. V6Z 2N3 CANADA BC TOLL FREE: 1-800-663-1385 web site: http://www.bcuc.com FACSIMILE: (604) 660-1102 IN THE MATTER OF the Utilities Commission Act, R.S.B.C. 1996, Chapter 473 and An Application by British Columbia Hydro and Power Authority (“BC Hydro”) for the Review of the F2007 and F2008 Revenue Requirements Application (“F07/08 RRA”) and for the Review of the 2006 Integrated Electricity Plan (“2006 IEP”) and the Approval of the 2006 Long-Term Acquisition Plan (“2006 LTAP”) BEFORE: R.H. Hobbs, Chair L.A. Boychuk, Commissioner A.J. Pullman, Commissioner May 24, 2006 O R D E R WHEREAS: A. In a letter dated March 15, 2006, BC Hydro applied for Commission approval to set its current rates as interim effective April 1, 2006 and in the same letter informed the Commission that it proposed to file its F07/08 RRA in late April 2006; and B. By Order No. G-32-06 dated March 23, 2006, the Commission approved current customer rates as interim effective April 1, 2006; and C. By Commission Order No. G-103-05 dated October 5, 2005, the Commission approved a Negotiated Settlement in the Resource Expenditure Acquisition Plan (“REAP”) proceeding. In the REAP Negotiated Settlement, BC Hydro committed to seek, pursuant to Section 45 (6.2) of the Utilities Commission Act (the Act, UCA”), regulatory approval of its 2006 LTAP, to be included with its 2006 IEP; and D. On March 29, 2006 BC Hydro filed, pursuant to Section 45 (6.1) of the Act, its 2006 IEP and 2006 LTAP with the Commission for review; and …/2
BRITISH COLUMBIA UTILITIES COMMISSION ORDER NUMBER G-59-06 2 E. The 2006 IEP is a long-term plan that describes how BC Hydro could meet customers electricity needs over a 20-year planning horizon and the resource options available to meet those needs under a variety of assumptions and risks; and F. The 2006 LTAP is an action plan that is supported by the 2006 IEP. It itemizes the actions BC Hydro intends to take in the next ten years to meet customers electricity needs as part of BC Hydros overall planning and resource acquisition process; and G. BC Hydro seeks an Order which: (i) states that the 2006 LTAP meets the requirements of Section 45 (6.1) of the UCA; (ii) makes specific determinations under Subsection 45 (6.2)(b) of the UCA with respect to certain planned expenditures; and (iii) approves the transmission LTAP plan and Contingency Plans for inclusion in the BC Hydros Network Integrated Transmission Service application; and H. In its cover letter dated March 29, 2006, BC Hydro proposed a Procedural Conference to assist with establishing a Regulatory Agenda for both its F07/08 RRA and the 2006 IEP and 2006 LTAP; and I. By Order No. G-37-06 the Commission established a Procedural Conference to hear submissions on the regulatory process for the review of the both the F07/08 RRA and the 2006 IEP and 2006 LTAP. The Procedural Conference was scheduled for May 19, 2006; and J. In a letter dated May 1, 2006, BC Hydro informed the Commission and all Intervenors and Interested Parties of a delay and that the balance of its F07/08 RRA would be filed towards the end of May 2006; and K. The Joint Industry Electric Steering Committee (“JIESC”) submitted to the Commission in a letter dated May 5, 2006 that participants should not be required to file Information Requests with respect to the 2006 IEP, 2006 LTAP or F07/08 RRA prior to the filing of the RRA because the Applications are intertwined. It submitted that the Procedural Conference be postponed to the week of June 19, 2006. The JIESC also …/3
BRITISH COLUMBIA UTILITIES COMMISSION ORDER NUMBER G-59-06 3 requested that the Commission reconsider its Order No. G-32-06 approving BC Hydros current rates as interim; and L. On May 10, 2006, the Commission issued a letter with a draft regulatory timetable and an accompanying Order No. G-51-06 (IEP Exhibit A-4) to address issues raised by Intervenors with respect to the delay by BC Hydro in filing the F07/08 RRA; and M. The Commission held a Procedural Conference on May 19, 2006 wherein the Commission Panel considered submissions on whether or not the Order on interim rates should be reconsidered; whether a Rate Design Application (“RDA”) should be filed; and the scheduling for the regulatory review of the 2006 IEP and 2006 LTAP, the F07/08 RRA and a RDA (if required by the Commission); and N. The Commission concluded that the Regulatory Timetable attached to IEP Exhibit A-4 should be amended. NOW THEREFORE the Commission orders as follows: 1. The request for reconsideration of Order No. G-32-06 on interim rates is approved. The Commission will issue Letter No. L-21-06 with Reasons attached that establishes a timetable for submissions. 2. BC Hydro is required to file a RDA. The date for filing the RDA will be decided after determining the oral hearing schedules for the two Applications in the Second Procedural Conference. The Regulatory Agenda is set out in Appendix A to this Order. 3. After the Second Procedural Conference, the Commission will issue a further Procedural Order and Regulatory Agenda for the review of the 2006 IEP and LTAP and the RRA. DATED at the City of Vancouver, in the Province of British Columbia, this 25 th day of May 2006 BY ORDER Original signed by: Robert H. Hobbs Chair Attachment Orders/BCH-IEP & F07RR_Amended Regulatory Timetable
SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER, B.C. V6Z 2N3 CANADA web site: http://www.bcuc.com An Application by British Columbia Hydro and Power Authority (“BC Hydro”) for the Review of the F2007 and F2008 Revenue Requirements Application (“F07/08 RRA”) and for the Review of the 2006 Integrated Electricity Plan (“2006 IEP”) and the Approval of the 2006 Long-Term Acquisition Plan (“2006LTAP”) AMENDED REGULATORY TIMETABLE ACTION BC Hydro filing of F07/08 RRA IEP and LTAP IRs to BC Hydro (BCUC No. 2 and Intervenor No. 1) BC Hydro Technical Workshop (Revenue Requirement Spreadsheet Model) RRA IRs to BC Hydro (BCUC No. 1) BC Hydro Response to IEP and LTAP IRs (BCUC No. 2 and Intervenor No. 1) BC Hydros Evidence re Project Evaluation RRA IRs to BC Hydro (Intervenor No. 1) IRs on Evidence re Project Evaluation (BCUC and Intervenor No. 1) BC Hydro Responses to RRA IRs (BCUC and Intervenor No. 1) BC Hydro Responses to Evidence re Project Evaluation IRs (BCUC and Intervenor IR No. 1) Second Procedural Conference (to address consolidation; further rounds of IRs; timetable for filing of evidence by Applicant and Intervenors and IRs thereon; scheduling of oral hearings; and any other matters) APPENDIX A to Order No. G-59-06 Page 1 of 1 TELEPHONE: (604) 660-4700 BC TOLL FREE: 1-800-663-1385 FACSIMILE: (604) 660-1102 DATE (2006) Monday, May 29 Monday, June 5 Monday, June 5 Thursday, June 22 Friday, June 30 Friday, June 30 Wednesday, July 5 Monday, July 10 Wednesday, July 26 Wednesday, July 26 Tuesday, August 1
 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.