Orders

Decision Information

Decision Content

LETTER NO. L-29-08 SIXTH FLOOR, 900 HOWE STREET, BOX 250 ERICH M. HAMILTON VANCOUVER, B.C. CANADA V6Z 2N3 COMMISSION SECRETARY TELEPHONE: (604) 660-4700 Commission.Secretary@bcuc.com BC TOLL FREE: 1-800-663-1385 web site: http://www.bcuc.com FACSIMILE: (604) 660-1102 Log No. 25481 VIA E-MAIL Scott_Stoness@kindermorgan.com June 23, 2008 Mr. D. Scott Stoness Vice President - Regulatory Kinder Morgan Canada Inc. 2700 300 5 th Avenue SW Calgary, Alberta T2P 5J2 Dear Mr. Stoness: Re: Trans Mountain (Jet Fuel) Inc. (“TMJ”) Reconsideration of Commission Order No. P-3-08 and Reasons for Decision In a letter dated May 27, 2008, TMJ requested that the Commission reconsider its decision to exclude the $67,090.19 of regulatory rate case costs (“RCC”) regarding the Application for Approval of Tolls and Accelerated Depreciation Reasons for Decision and Commission Orders No. P-3-08 and P-5-08. TMJ also requested that it be allowed to recover the RCC over the remaining amortization period from 2009 to 2012. On March 14, 2008, TMJ submitted its 2008 Tariff Filing as required by Commission Order No. P-3-08 (the Filing”). TMJ informed the Commission on April 2, 2008, that the billing of $7,689.81 for Commission Costs related to the Application was not an anticipated cost in the Filing and not included in the forecast for hearing costs. By Commission Order No. P-5-08, the Panel allowed the recovery of $147,689.81 of hearing costs. TMJ is of the opinion that the Commission has erred in its determination of costs claimed, and that there is just cause to reconsider the decision. TMJ further submits that it is appropriate in the circumstances to dispense with the two-step reconsideration process and proceed directly to a consideration of the merits of the reconsideration. With respect to TMJs request for reconsideration, the Commission normally follows the practice outlined in the Commissions Reconsideration Criteria which is outlined in the Commissions document, Understanding Utility Regulation, A Participants Guide to the BC Utilities Commission”. Although a request for reconsideration usually proceeds through a two-phase process, in the situation at hand the Commission accepts the position of TMJ that the matter should proceed directly to a reconsideration. …/2
2 LETTER NO. L-29-08 Therefore, the Commission establishes a reconsideration of the RCC based on the merits of the matter as set out in the submission of TMJ. In considering the TMJ request the Commission is of the understanding that TMJ will not wish to file any further submissions on this matter, other than a reply to any submissions from the intervenors in the proceeding that lead to the Order, should any submissions be filed. The Commission requests that TMJ confirm this understanding by Friday, June 27, 2008. The Commission will, by copy of this letter, provide an opportunity for the intervenors of record to comment on TMJs request for reconsideration of the RCC. Comments, if any, from the intervenors must be submitted by Monday, July 7, 2008 with a copy to TMJ. If comments are submitted by the intervenors, TMJ is provided an opportunity to reply by Friday, July 11, 2008. Yours truly, Original signed by Erica M. Hamilton SM/cms Enclosure Cc: Registered Intervenors Matthew Gikhas, Fasken Martineau DuMoulin LLP PF/TMJF Reconsider P-3-08/L-29-08_Phase 2 Reconsider Timetable
 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.