                                          SIXTH FLOOR900 HOWE STREETBOX 250  VANCOUVERB.C.  V6Z 2N3   CANADA  web sitehttp://www.bcuc.com  IN THE MATTER OF  the Utilities Commission ActR.S.B.C1996Chapter 473    and    An Application by British Columbia Hydro and Power Authority  for Review of the F2009 and F2010 Revenue Requirements Application    BEFORE LAOHaraPanel Chair    RJMilbourneCommissioner    AARhodesCommissioner    O  R  D  E  R  WHEREAS   A. British Columbia Hydro and Power Authority (“BC Hydro”) filed on February 202008pursuant to  sections 58 to 61 of the Utilities Commission Act (“the Act”), its F2009 and F2010 Revenue Requirements  Application foramong other thingsapproval of acrosstheboard rate increases of 6.56 percent and  8.21 percenteffective April 12008 and April 12009respectivelyand approval of a reduction of the  Deferral Account Rate Rider from 2.0 percent to 0.5 percenteffective April 12008 (the “F09/F10 RRA” or  Application”); and    B. The Application also sought refundable interim relief pursuant to sections 58 to 61 and section 90 of the Act  to allow BC Hydro to increase its rates by 6.56 percent on an acrosstheboard basis and to decrease its  Deferral Account Rate Rider from 2.0 percent to 0.5 percentboth effective April 12008pending a full  hearing into the F09/F10 RRA and orders subsequent to that hearingon the basis that on April 12008  BC Hydros current rates would otherwise no longer be fairjustsufficient and not unduly discriminatory and    C. On February 222008 the Commission issued Letter L508 that included establishing the regulatory process  and timetable for the F09/F10 RRA and the Transmission Service Rate Repricing Application (“TSR Repricing  Application”) and for parties to addressby written submissionthe BC Hydro request to implement interim  rates effective April 12008and     D. On February 252008 the Commission issued Order G2108 establishing the Regulatory Timetable for the  F09/F10 RRA.  The Regulatory Timetable included a Workshop on March 62008Commission and  Intervenor Information RequestsResponses by BC Hydroand a Procedural Conference on April 282008.   The Procedural Conference was to consider further process for the F09/F10 RRATSR Repricing Application and Residential Inclining Block (“RIB”) Applicationand              BRIT ISH  COLU   MBIA   UTIL IT IES  COM   MISSION               ORDER         NUMBER   G  12208            TELEPHONE:  (604)  6604700  BC TOLL FREE:  18006631385  FACSIMILE:  (604)  6601102    August 252008  …/2 
  BRIT ISH  COLUMBIA   UTIL IT IES  COMMISSION         ORDER     NUMBER   G12208  2  E. On February 282008 the Commission issued Order G2808 that included a requirement for the publication  of a Notice of Applicationsand    F. On March 142008 the Commission issued Order G4008 that approved interim refundable rate changes for  the 6.56 percent acrosstheboard rate increase and the decrease in BC Hydros Deferral Account Rate Rider  from 2.0 percent to 0.5 percentboth effective April 12008and    G. At the April 282008 Procedural Conference BC Hydro presented a “Strawman Regulatory Timetable” that  coordinated the three applications.  For the F09/F10 RRABC Hydro proposed a regulatory timetable that  included a Negotiated Settlement Process (“NSP”).  BC Hydro also proposed an Oral Public Hearing  commencing on MondayOctober 62008 for issues not resolved in the NSP.  BC Hydro also proposed a Pre hearing Conference one week before the commencement of the Oral Public Hearingand    H. At the Procedural Conference BC Hydro proposed that all issues arising from the F09/F10 RRAexcept for  Demand Side Management (“DSM”) issuesshould be included within the scope of the NSP.  BC Hydro was of  the view that DSM expenditures during the test period are more appropriately addressed in the context of  the LongTerm Acquisition Plan (“LTAP”) proceedingand that the anticipated demand response to those  expenditures should also be resolved in the LTAP proceeding.  In additionBC Hydro was of the view that the  appropriate amortization period for DSM expenditures is also more appropriately addressed in the context  of the LTAP proceedingand    I. All the Intervenors in attendance were supportive of or did not take a position on the BC Hydro proposed  regulatory timetable for the F09/F10 RRA except for the City of New Westminsterand    J. The Commission considered the submissions received at the Procedural Conference and by Order G7808  dated April 30,2008 established a Regulatory Timetable for review of the F09/F10 RRA through an Oral  Public Hearing  to commence on MondayOctober 62008 at 9:00 a.m., if the NSP scheduled to commence  on August 182008 did not conclude in an agreementand    K. On July 22008 BC Hydro filed an Evidentiary Update to the F09/F10 RRA that included F2008 actual results  and F2008 closing balances of all regulatory and deferral accountsan update on the DSM energy savings  and expenditures to be consistent with forecasts in BC Hydros 2008 LTAPas well as updated forecasts for  energy salesrevenues and cost of energy.  If all these changes are approved the final rates for F2009 and  F2010 would reflect annualized rate increases of approximately 9 percent per year.  BC Hydro proposes  deferring forecast increases on those costs that are subject to deferral but flowing through into rates the  forecast net reduction in those costs not subject to deferral.  Based on this approach BC Hydro proposes  final rate increases of 5.96 percent and 8.12 percent effective April 12008 and 2009 respectivelyand  …/3 
    BRIT ISH  COLUMBIA   UTIL IT IES  COMMISSION         ORDER     NUMBER   G12208  3    L. On July 302008 MrStuart Meade issued a late Information Request to BC Hydro.  The Regulatory Timetable  attached to Order G7808 established the Information Request No2 deadline of May 212008.  On August  12008 the Commission advised BC Hydro that it may provide a response to the late Information Request  before the commencement of the NSP discussions if time and resources permit.  On August 12008 BC  Hydroin its letter to the Commission indicated that the late Information Request with 82 questions was  unreasonable.  HoweverBC Hydro indicated that it would be prepared to answer MrMeades questions  through the oral hearing should the NSP beginning on August 182008 not be successful.  On August 62008  BC Hydro wrote to MrMeade advising that it was unable to respond to his Information Request prior to  August 182008and    M. On August 132008the Canadian Office and Professional Employees Union Local 378 (“COPE”) filed a  request for leave to submit evidence for the NSP/hearing since the Intervenor Evidence deadline of July 29 2008 established by Order G7808 had passed.  COPEin its requestincluded a summary of its evidence.   On August 132008BC Hydro objected to the late filing of the evidence because it would not allow  Information Requests to be issued and responses received prior to the NSP.  BC Hydro noted that  participants to an NSP are free to bring any issues to the table in the NSP regardless of whether evidence has  been filed or not.  Depending on the outcome of the NSPBC Hydro stated that it may not maintain its  objectionand    N. On August 132008the Joint Electricity Steering Committee (“JIESC”) filed a letter requesting that the  Commission cancel the NSP and proceed to the full public hearing on MondayOctober 62008.  By letter  dated August 142008 the British Columbia Old Age Pensioners Organization et al. (“BCOAPO”) supported  the JIESCs request.  Also on August 142008the Rental Owners and Managers Society of BC (“ROMS BC”)  concurred with the August 13 and 142008 submissions of the JIESC and BCOAPO respectively.  The same  day BC Hydro replied to the JIESCs and BCOAPOs letters of August 13 and 142008 noting it would not be  worthwhile to proceed with the NSP in the circumstancesand    O. By Order G11908 the Commission cancelled the NSP.  The Order also established a Prehearing Conference  on August 212008 to receive submissions from Intervenors and BC Hydro on a regulatory timetable and the  scope of issues to be addressed in the review of the F09/F10 RRAthe late Information Request by MrStuart  Meadethe request by COPE to file Intervenor Evidenceand any other mattersand     P. The Prehearing Conference was held on August 212008  and attended by BC Hydro and the following  IntervenorsBC Transmission Corporationthe Terasen UtilitiesIndependent Power Producers Association  of BCCity of New Westminsterthe JIESCElk Valley Coal CorporationCommercial Energy Consumers of  British ColumbiaBCOAPOBC Sustainable Energy Association and Sierra Club of Canada BC ChapterCOPE and MrAlan Waitand    Q. The Commission has reviewed the submissions and concludes that a determination is required   . . . /4 
    BRIT ISH  COLUMBIA   UTIL IT IES  COMMISSION         ORDER     NUMBER   G12208  4      NOW THEREFORE the Commission ordersfor the Reasons contained in Appendix A (attachedthat   1. BC Hydros proposal to amend the Regulatory Timetable as established by Order G7808 to review the  Application through a written hearing process is denied.  The Application will be dealt with by way of the  previously agreed and scheduled Oral Public Hearing commencing on October 62008 at 9:00 a.min the  Commission Hearing Room on the Twelfth Floor at 1125 Howe StreetVancouverB.C   2. The scope of the F09/F10 RRA proceeding will remain as defined in Order G7808   3. BC Hydro is not required to respond in writing to the late Information Request filed by MrMeade on July 30 2008   4. Leave is granted to COPE to file its application for late evidence and the application together with the  proposed evidence are to be filed by no later than FridaySeptember 52008.  BC Hydro and the Intervenors  are to file their submissionsif anyon the COPE application and proposed evidence by Wednesday September 102008.  The submissions should address whether the proposed COPE evidence is within the  scope of the proceedingits relevance to the proceedingand whether the party to the proceeding would be  prejudiced if the proposed evidence is accepted as evidence for the purposes of the record.  COPE is to file  its replyif anyto the submissions of BC Hydro and the Intervenors by FridaySeptember 122008   5. If BC Hydro wishes to apply to the Commission for an order consolidating the F09/F10 RRA and the LTAP  proceedingsit should make such application to the Commission in the ordinary course     DATED at the City of Vancouverin the Province of British Columbiathis              25 th             day of August 2008     BY ORDER    Original signed by     LAOHara    Panel Chair  ORDERS/G12208_BCHF20092010RR_Reasons for Decision 
APPENDIX A  to Order NoG12208  Page 1 of 5      An Application by British Columbia Hydro and Power Authority  for Review of the F2009 and F2010 Revenue Requirements Application  REASONS FOR DECISION 1.0 BACKGROUND  British Columbia Hydro and Power Authority (“BC Hydro”) filedon February 202008pursuant to sections 58 to  61 of the Utilities Commission Act (“the Act”), its F2009 and F2010 Revenue Requirements Application for among other thingsapproval of acrosstheboard rate increases of 6.56 percent and 8.21 percenteffective April  12008 and April 12009respectivelyand approval of a reduction of the Deferral Account Rate Rider from 2.0  percent to 0.5 percenteffective April 12008 (the “F09/F10 RRA” or “Application”).  The Application also sought  refundable interim relief pursuant to sections 58 to 61 and section 90 of the Act to allow BC Hydro to increase its  rates by 6.56 percent on an acrosstheboard basis and to decrease its Deferral Account Rate Rider from 2.0  percent to 0.5 percentboth effective April 12008pending a full hearing into the F09/F10 RRA and orders  subsequent to that hearingon the basis that on April 12008 BC Hydros current rates would otherwise no  longer be fairjustsufficient and not unduly discriminatory   At the April 282008 Procedural Conference BC Hydro presented a “Strawman Regulatory Timetable” for the  Application.  BC Hydros proposed regulatory timetable included a Negotiated Settlement Process (“NSP”) with  an Oral Public Hearing commencing on MondayOctober 62008 for issues not resolved in the NSP.  The  Commission considered the submissions received at the Procedural Conference and by Order G7808  established a Regulatory Timetable for the review of F09/F10 RRA through an Oral Public Hearing to commence  on MondayOctober 62008 at 9:00 a.min the event that the NSP scheduled to commence on August 182008  did not conclude in an agreement.      On July 22008 BC Hydro filed an Evidentiary Update to its F09/F10 RRA that included F2008 actual results and  F2008 closing balances of all regulatory and deferral accountsan update on the DSM energy savings and  expenditures to be consistent with forecasts in BC Hydros 2008 Long Term Acquisition Plan (“LTAP”), as well as  updated forecasts for energy salesrevenues and cost of energy.   If all these changes are approved the final  rates for F2009 and F2010 would reflect annualized rate increases of approximately 9 percent per year.   BC Hydro proposes deferring forecast increases on those costs that are subject to deferral but flowing through  into rates the forecast net reduction in those costs not subject to deferral.  Based on this approach BC Hydro  proposes final rate increases of 5.96 percent and 8.12 percent effective April 12008 and 2009 respectively   On August 132008the Joint Industry Electricity Steering Committee (“JIESC”) filed a letter stating that while it  initially supported the holding of an NSP on the F09/F10 RRA it no longer did so.  By letter dated August 142008  the British Columbia Old Age Pensioners Organization et al. (“BCOAPO”) supported the JIESCs request that the  NSP be cancelled and the matter proceeds to the Oral Public Hearing scheduled for October 62008.  Also on  August 142008the Rental Owners and Managers Society of BC concurred with the submissions of the JIESC  and BCOAPO.  By letter also dated August 142008 BC Hydro replied to the JIESC and BCOAPO stating that it  regretted the additional burden that their positions will create but felt that without the willing participation of  these two Intervenors it was not worthwhile to proceed with the NSP
APPENDIX A  to Order NoG12208  Page 2 of 5    By Order G11908 dated August 152008 the Commission cancelled the NSP for the F09/F10 RRA scheduled to  commence on MondayAugust 182008 and established a Prehearing Conference for August 212008 to  receive submissions from Intervenors and BC Hydro on a regulatory timetable and the scope of issues to be  addressed in the review of the F09/F10 RRAa late information request by MrStuart Meadea request by  Canadian Office and Professional Employees Union Local 378 (“COPE”) to file late Intervenor Evidenceand any  other matters     2.0 PREHEARING CONFERENCE  The Prehearing Conference on August 212008 was attended by BC Hydro and the following Intervenors BC Transmission Corporationthe Terasen UtilitiesIndependent Power Producers Association of BC (“IPPBC”),  City of New WestminsterJIESCElk Valley Coal CorporationCommercial Energy Consumers of British Columbia  (“CEC”), BCOAPOBC Sustainable Energy Association and Sierra Club of Canada BC Chapter (“BCSEA et al.), COPE and MrAlan Wait     3.0 ISSUES  Issues discussed at the Prehearing Conference were   BC Hydros Proposal to Amend Order G7808 to review the Application through a Written Hearing  Scope of the F09/F10 RRA Proceeding  Late Information Request from MrMeade  COPE Letter of August 132008 and COPE Request for Leave to File Evidence  Consolidation of the F09/F10 RRA and LTAP Applications    The Commission Panel has reviewed the submissions on the issues.  The issues are addressed below     3.1 BC HYDROS PROPOSAL TO AMEND ORDER G7808 TO REVIEW THE APPLICATION THROUGH A  WRITTEN HEARING  At the Prehearing ConferenceCounsel for BC Hydro submitted that the review of the F09/F10 RRA should  proceed by way of a written hearing process rather than the scheduled oral hearing.  BC Hydro believes that  there is a very extensive and sufficient evidentiary record that includes Information Requests and Intervenor  Evidence.  BC Hydro submits that a written process would take less time and resources of the utility.  BC Hydro  proposed a timetable for Final ArgumentIntervenor Argumentsand Reply Argument for the written process   Review of the F09/F10 RRA by way of a written hearing was addressed by the JIESCElk Valley Coal Corporation the CECBCOAPOBCSEA et al., COPEand MrWaitall of whom either objected strongly to the cancellation of  the previously agreed and scheduled Oral Public Hearing or expressed a preference for it.  The JIESC argued that  the Information Requests contained in the written record have a rolebut do not replace live crossexamination.   This view was echoed by other Intervenors.  The Terasen Utilities and the IPPBC did not take a position on  BC Hydros requestother than to note thatif required, “contentious issues” could be referred to an oral phase  
APPENDIX A  to Order NoG12208  Page 3 of 5  The Commission Panel notes that the “Strawman Regulatory Timetable” submitted by BC Hydro at the April 28 2008 Procedural Conference included both the NSP and the Oral Public Hearing (if requiredand their dates and  that it was subsequently approved by the Commission in the Regulatory Timetable set out in Order G7808.   Having reviewed the submissions of BC Hydro and the Intervenorsthe Commission Panel is not persuaded that  a written hearing process would be more expeditious or involve less time and resources when considering all  parties.  The Commission Panel accepts the argument that Information Requests do not replace  crossexamination in all circumstances and is therefore not persuaded that it is in the public interest that the  Regulatory Timetable established in Order G7808 with an Oral Public Hearing commencing on October 62008  be varied. BC Hydros proposal to amend the Regulatory Timetable as established by Order G7808 to review the  Application through a written hearing process is denied.  The Application will be dealt with by way of the  previously agreed and scheduled Oral Public Hearing commencing on October 62008 at 9:00 a.min the  Commission Hearing Room on the Twelfth Floor at 1125 Howe StreetVancouverB.C   Order G7808 contemplated a Signoff Date for the Negotiated Settlement of September 192008 andif  necessarya Prehearing Conference on September 292008.  The Signoff Date is moot due to the cancellation  of the NSP and the Prehearing Conference on September 292008 is cancelled     3.2 SCOPE OF THE F09/F10 RRA PROCEEDING  BC Hydro submitted that no scoping determinations are required except for its concern in respect of issues  raised by COPE regarding the governments energy policy and its validity and its cost   Subsequentlya number of Intervenors provided their views on the scope of the F09/F10 RRA proceeding.  IPPBC  noted that COPEs issues related to the law are out of scope for the proceeding.  The JIESC considers that the  current DSM expenditures and the Site C expenditures could be moved to the revenue requirements hearing.   The CEC believes that questions which talk about energy policy initiatives should be within the scope of this  proceeding as they relate to expenditures of BC Hydro.  BCOAPO cited a number of issues that it is interested in  exploring in the proceeding.  BCSEA et alalso cited a number of issues that it is concerned with including a  variety of initiatives such as Burrard Thermal Generationexpenditures for the legislated “smart meter”  initiativeSite Cand First Nation expenditures.  COPE expressed interest in a number of issues including smart  metersthe Accenture contractand selfsufficiency and its impact on revenue requirements and rates.  MrWait  noted some issues that he considers of interest in the revenue requirements   In responseCounsel for BC Hydro stated that what should be out of scope are those things that BC Hydro is  obliged to do such as selfsufficiency.  BC Hydro believes that the reason for implementing government policy is  out of scope but the execution of government policy is within scope   The Commission Panel notes that costs that impact rates in the test years are usually considered within scope in  a revenue requirements application unless explicitly excludedThe Commission Panel directs that the scope of  the F09/F10 RRA proceeding will remain as defined in Order G7808  
APPENDIX A  to Order NoG12208  Page 4 of 5    3.3 LATE INFORMATION REQUEST FROM MRMEADE  BC Hydro contends that the late Information Request from MrMeade issued on July 302008 should not be  answered in writingIt had previously offered to answer the questions at the oral hearing if the NSP was not  successful.  The CEC did not take a position on the late Meade Information Request but noted that the  Commission should have some reluctance to change its timelines absent strong reason for change.  Other  Intervenors noted that the Commission should be cautious about allowing late Information Requests   MrMeade was not present at the Prehearing Conference.  He did not make a written submission prior to the  Prehearing Conferencedid not indicate that he would not be in attendance and accordingly made no  submissions in support of his request.     The Commission Panel confirms that BC Hydro is not required to respond in writing to the late Information  Request filed by MrMeade on July 302008     3.4 COPE LETTER OF AUGUST 132008 AND COPE REQUEST FOR LEAVE TO FILE EVIDENCE  At the Prehearing Conference BC Hydro confirmed that it did not object to the COPE two page letter of  August 132008and BC Hydros response to it of that datebeing entered as evidence.  HoweverBC Hydro  objects to the filing of the documents attached to the COPE letter   The Commission Panel directs that the twopage letter filed by COPE on August 132008without its  attachmentsbe included as part of the F09/F10 RRA evidentiary record and that the BC Hydro letter of August  132008 in response to the COPE letter also be entered into the evidentiary record   At the Prehearing Conference COPE explained that it was unable to file its proposed evidence earlier due to a  number of factors.  COPE stated that its evidence would address a number of issues including operating costs the Accenture contractand impact of government policy and tax measures on revenue requirements.  COPE  explained that if granted leave it would provide a COPE Witness Panel to address the COPE evidence at the Oral  Hearing.  HoweverCOPE indicated that it would not be able to file it application for a couple of weeks    BC Hydros position is that COPE should be obligedin a timely manner with a fixed dateto file an application  attaching the evidence.  Counsel for BC Hydro stated that the evidence should not be placed on the record of the  proceeding until the Commission concludes that it should bebased on the submissions that address the  admissibility of the evidence   The Commission Panel grants leave to COPE to file its application for late evidence and the application  together with the proposed evidence are to be filed by no later than FridaySeptember 52008.  BC Hydro and  the Intervenors are to file their submissionsif anyon the COPE application and proposed evidence by  WednesdaySeptember 102008.  The submissions should address whether the COPE  proposed evidence is  within the scope of the proceedingits relevance to the proceedingand whether the party to the proceeding  would be prejudiced if the proposed evidence is accepted as evidence for the purposes of the record.  COPE is  to file its replyif anyto the submissions of BC Hydro and the Intervenors by FridaySeptember 122008  
APPENDIX A  to Order NoG12208  Page 5 of 5    3.5 CONSOLIDATION OF THE F09/F10 RRA AND LTAP APPLICATIONS    B.CHydro made submissions concerning the possibility of its applying to consolidate the F09/F10 RRA  proceeding with the LTAP proceeding into a single review process.  BC Hydro also suggested that a procedural  conference both for LTAP participants and F09/F10 RRA participants could be held during the week of  September 2 nd  to address the consolidation   If BC Hydro wishes to apply to the Commission for an order consolidating the Application and the LTAP  proceedingit should make such application to the Commission in the ordinary course