IN THE MATTER OF
the Utilities Commission Act, R.S.B.C. 1996, Chapter 473
and
An Application by Pacific Northern Gas (N.E.) Ltd.
(Fort
St. John/Dawson Creek and Tumbler Ridge Divisions)
For Approval of its 2011 Revenue Requirements
for the PNG (N.E.) Service Area
BEFORE: D.A. Cote, Panel Chair/Commissioner
N. MacMurchy, Commissioner December 7, 2010
D. Morton, Commissioner
O R D E R
WHEREAS:
A. Pacific Northern Gas (N.E.) Ltd. [PNG (N.E.)] Fort St. John/Dawson Creek (FSJ/DC) and Tumbler Ridge (TR) Divisions filed on November 30, 2010 with the British Columbia Utilities Commission (BCUC or Commission), pursuant to sections 58 to 61 of the Utilities Commission Act (the Act), its 2011 Revenue Requirements Application (Application) to, among other things, amend its delivery rates;
B. The Application also seeks refundable interim relief pursuant to section 58 to 61, 89 and 90 of the Act to allow PNG (N.E.) to amend its rates on an interim basis, effective January 1, 2011, pending the hearing of the Application and orders subsequent to that hearing, on the basis that on January 1, 2011 PNG (N.E.)’s rates would otherwise no longer be fair, just and not unduly discriminatory;
C. PNG (N.E.)’s FSJ/DC Division projects a revenue deficiency of $2.47 million comprised of a net increase in cost of service of $2.13 million and a decrease in margin of approximately $0.34 million;
D. PNG (N.E.)’s FSJ Division seeks Commission approval to increase the delivery charge for residential service by $0.801/GJ from $2.660/GJ to $3.461/GJ representing an increase of 30.1 percent compared to the 2010 delivery rate, and for small commercial service by $0.542/GJ from $2.307/GJ to $2.849/GJ corresponding to an increase of 23.5 percent compared to the 2010 delivery rate;
E. PNG (N.E.)’s DC Division seeks Commission approval to increase the delivery charge for residential service by $0.801/GJ from $2.462/GJ to $3.263/GJ representing an increase of 32.5 percent compared to the 2010 delivery rate, and for small commercial service by $0.542GJ from $1.770/GJ to $2.312/GJ corresponding to an increase of 30.6 percent compared to the 2010 delivery rate;
F. The PNG (N.E.) TR Division projects a revenue sufficiency of $25,000 comprised of a net decrease in cost of service of $44,000 and a decrease in margin of approximately $19,000;
G. The PNG (N.E.) TR Division seeks Commission approval to decrease the delivery charge for residential service by $0.122/GJ from $4.781/GJ to $4.659/GJ representing a decrease of 2.6 percent compared to the 2010 delivery rate, and for small commercial service by $0.090/GJ from $4.218/GJ to $4.128/GJ corresponding to a decrease of 2.1 percent compared to the 2010 delivery rate;
H. PNG(N.E.) proposed a Preliminary Regulatory Timetable and considers a Negotiated Settlement Process (NSP) to be the most efficient process for the review of the Application;
I. The Commission considers establishing a Preliminary Regulatory Timetable including a Workshop for the preliminary review of the Application, and to allow Interveners to make written submissions on a formal review process, is necessary and in the public interest.
NOW THEREFORE pursuant to sections 58 to 61, 89 and 90 of Act the Commission orders as follows:
1. The Commission approves for PNG (N.E.) the delivery rates and the RSAM rider set forth in the Application on an interim basis, effective January 1, 2011. Any differences between the 2011 interim and permanent delivery rates that are determined by the Commission following final disposition of the Application are subject to refund/recovery, with interest at the average prime rate of PNG (N.E.)’s principal bank for its most recent year, in the manner as set out by a Commission Order that establishes permanent rates.
2. The Preliminary Regulatory Timetable for the Application is as set out in Appendix A to this Order. The dates and events in Appendix A after January 31, 2011 are subject to further Order establishing the review process and the regulatory timetable for review of the Application.
3. The Commission will hold a Workshop to review the issues in the Application on Thursday, December 16, 2010 commencing at 11.00 a.m. in the BCUC Offices, Sixth Floor, 900 Howe Street, Vancouver, BC.
4. PNG (N.E.) is to provide a copy of this Commission Order, by e-mail where possible, to all parties who participated in the PNG (N.E.) 2010 Revenue Requirements Application proceedings.
5. PNG (N.E.) will publish in display-ad format, the Notice of Application and Workshop as attached as Appendix B to this Order, as soon as reasonably possible following the issuance of this Order, but no later than December 10, 2010 for the Vancouver Sun and The Province, and no later than December 15, 2010 for such other appropriate news publications as may properly provide adequate notice to the public in its service areas.
6. The Application and supporting material will be made available for inspection at public libraries in Fort St. John, Dawson Creek, and Tumbler Ridge, and at the Head Office of PNG (N.E.) at Suite 950, 1185 West Georgia Street, Vancouver, B.C., V6E 4E6 and at the British Columbia Utilities Commission, Sixth Floor, 900 Howe Street, Vancouver, B.C., V6Z 2N3. PNG will also make the Application available on PNG’s website at hhtp://www.png.ca.
7. Interveners and Interested Parties should register with the Commission via E-Mail or in writing, by December 24, 2010, of their intention to intervene. Interveners should specifically state the nature of their interest in the Application, and identify generally the nature of the issues that they intend to pursue during the proceeding and the nature and extent of the anticipated involvement in the Application. The Commission is to receive submissions from Interveners by January 31, 2011 on the appropriate regulatory review process that should be followed in the review of the Application.
8. Interveners intending to apply for participant assistance must submit a budget estimate by February 2, 2011 consistent with the Commission’s Participant Assistance/Cost Award Guidelines and Order G-72-07. Copies are available upon request, or can be downloaded from the Commission’s website at hhtp://www.bcuc.com.
9. The Commission will accept, subject to timely filing by PNG (N.E.), amended Gas Tariff Rate Schedules in accordance with the terms of this Order. PNG (N.E.) is to provide notice of the interim rates to customers via a bill message, to be reviewed in advance by Commission Staff to confirm compliance with this Order.
DATED at the City of Vancouver, in the Province of British Columbia, this 8th day of December 2010.
BY ORDER
Original signed by:
D.A. Cote
Panel Chair/Commissioner
Attachments
APPENDIX A
to Order G-183-10
Page 1 of 1
Pacific Northern Gas (N.E.) Ltd.
Application for Approval of 2011 Revenue Requirements
for PNG (N.E.) Service Area
PRELIMINARY REGULATORY TIMETABLE
ACTION |
DATES |
Workshop No. 1 |
Thursday, December 16, 2010 |
Intervener and Interested Parties Registration |
Friday, December 24, 2010 |
Commission Information Request No. 1 |
Friday, December 31, 2010 |
Intervener Information Request No. 1 |
Friday, January 14, 2011 |
PNG Responses to Information Request No. 1 |
Friday, January 28, 2011 |
Intervener Comments regarding Regulatory Process |
Monday, January 31, 2011 |
Workshop No. 2 – pending |
Wednesday, February 9, 2011 |
Potential commencement date for Negotiated Settlement Process |
Wednesday, February 16, 2011 |
NOTICE OF WORKSHOP
Date: |
Thursday, December 16, 2010 |
Time: |
11.00 a.m. |
Location: |
BCUC Office 900 Howe Street, Sixth Floor Vancouver, BC |
Pacific Northern Gas (N.E.) Ltd.
Application for Approval of 2011 Revenue Requirements
for PNG (N.E.) Service Area
NOTICE OF REVENUE REQUIREMENTS APPLICATION AND WORKSHOP
NOTICE OF WORKSHOP
Date: |
Thursday, December 16, 2010 |
Time: |
11.00 a.m. |
Location: |
BCUC Office 900 Howe Street, Sixth Floor Vancouver, BC |
THE APPLICATION
Pacific Northern Gas (N.E.) Ltd. [PNG (N.E.)] Fort St. John/Dawson Creek (FSJ/DC) and Tumbler Ridge (TR) Divisions filed on November 30, 2010 with the British Columbia Utilities Commission (Commission), pursuant to sections 58 to 61, 89 and 90 of the Utilities Commission Act (the Act), its 2011 Revenue Requirements Application (Application) to, among other things, amend its delivery rates, on an interim and refundable basis effective January 1, 2011 to be made permanent following the Commission’s review process.
The Commission wishes to ensure that affected parties have an opportunity to understand the Application and its implications for customer rates. The Commission also wishes to hear from affected parties before determining the public process necessary for the disposition of the Application.
For the FSJ/DC Division, the delivery rate increase is estimated to be approximately $0.801 per GJ for a residential customer. Based on the gas cost recovery and GCVA rate riders effective October 1, 2010 thru December 31, 2010 the overall average bundled rate increase for a typical residential customer consuming 109.1 GJ per year, is 8.2 percent, an increase of $82 per year. The delivery rate increase for a small commercial customer is estimated to be $0.542. Similarly, commercial customer consuming 525 GJ per year, the increase is 6.1 percent or $257 per year.
For the TR Division the delivery rate increase is estimated to be approximately $0.122 per GJ for a residential customer. This represents an increase of 2.6 percent compared to the 2010 delivery rate. The delivery rate increase for a small commercial customer is estimated to be $0.090 per GJ corresponding to an increase of 2.1 percent compared to the 2010 delivery rate.
For the TR Division based on the gas cost recovery and GCVA rate riders effective October 1, 2010 thru December 31, 2010 the overall average bundled rate increase for a typical residential customer consuming 86 GJ per year, is 0.3 percent, an increase of $2 per year. Similarly, for a small commercial customer consuming 516 GJ per year, the increase is 0.8 percent or $28 per year.
THE REGULATORY PROCESSES
The Commission will hold a Workshop on Thursday December 16, 2010 in Vancouver, BC to discuss issues in the Application.
PUBLIC INSPECTION OF THE APPLICATION
The Application and supporting material will be made available for inspection at public libraries in Fort St. John, Dawson Creek, and Tumbler Ridge, and at the Head Office of PNG (N.E.) at Suite 950, 1185 West Georgia Street, Vancouver, B.C., V6E 4E6 and at the British Columbia Utilities Commission, Sixth Floor, 900 Howe Street, Vancouver, B.C., V6Z 2N3.
The Application will also be available for viewing on the
PNG website at www.png.ca
(www.png.ca/ir_utilities.cfm )
and on the Commission’s website at www.bcuc.com,
which also contains detailed materials related to the Application including
Commission Orders and Intervenor materials (http://www.bcuc.com/Proceeding.aspx?ApplicationType=Current
).
REGISTERING TO PARTICIPATE
Persons who expect to actively participate in the review processes and the Workshop should register as Interveners. Interveners will receive copies of the Application, all correspondence and filed documents. Persons not expecting to actively participate should register with the Commission as Interested Parties and will receive a copy of the Application summary and the Commission’s Decision.
Interveners and Interested Parties should inform the Commission Secretary, in writing or by online web registration, by Friday, December 24, 2010 of their intention to become Interveners or Interested Parties with respect to the Application.
All submissions and/or correspondence received from active participants or the general public relating to the Application will be placed on the public record and posted to the Commission’s web site.
FURTHER INFORMATION
For further information, please contact Ms. Erica M. Hamilton, Commission Secretary, or Mr. Philip Nakoneshny, Director, Rates and Finance, as follows:
Telephone: (604) 660-4700 or (B.C. Toll Free) 1-800-663-1385
Facsimile: (604) 660-1102
E-mail: commission.secretary@bcuc.com