Orders

Decision Information

Decision Content

 

Via Email

regulatory.affairs@terasengas.com                                                       February 11, 2010

 

 

 

Mr. Tom Loski

Chief Regulatory Officer

Terasen Gas Inc.

16705 Fraser Highway

Surrey, BC   V4N 0E8

 

Dear Mr. Loski:

 

Re:  Terasen Gas Inc.

Gas Supply Mitigation Incentive Program for 2008/09

 

Further to Terasen Gas’ December  31, 2009 filing, the Commission accepts the calculation of an incentive payment of $1,102,795 and issues the attached Commission staff report entitled “Staff Overview Report - Gas Supply Mitigation Incentive Program (GSMIP) 2008/09.”

 

                                                                                                                                Yours truly,

 

                                                                                                                                Original signed by:

                                                                                                                                A. Cormack

 

                                                                                                                        For :Erica Hamilton

 

RB/ac

Enclosure

cc:           Interested Parties

 

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.