Via Email
regulatory.affairs@terasengas.com February 11, 2010
Mr. Tom Loski
Chief Regulatory Officer
Terasen Gas Inc.
16705 Fraser Highway
Surrey, BC V4N 0E8
Dear Mr. Loski:
Re: Terasen Gas Inc.
Gas Supply Mitigation Incentive Program for 2008/09
Further to Terasen Gas’ December 31, 2009 filing, the Commission accepts the calculation of an incentive payment of $1,102,795 and issues the attached Commission staff report entitled “Staff Overview Report - Gas Supply Mitigation Incentive Program (GSMIP) 2008/09.”
Yours truly,
Original signed by:
A. Cormack
For :Erica Hamilton
RB/ac
Enclosure
cc: Interested Parties