                                                                                                                               August 26, 2010

 

 

 

FortisBC – 2011 Capital Expenditure Plan

                                                Exhibit  a-4

TO:         Mr. Dennis Swanson

                Director, Regulatory Affairs                                                         Registered Interveners

                Regulatory Affairs Department

                FortisBC Inc.

 

 

 

Re:  FortisBC Inc.

Project No. 3698603/Order G-112-10

Application for Approval of the 2011 Capital Expenditure Plan

 

Further to the August 4, 2010 Workshop in Kelowna, the Commission grants the requests from Interveners to amend the filing date for Intervener Information Requests No. 1 to Wednesday, September 10, 2010.

 

The Amended Regulatory Timetable is attached as Appendix A.

 

                                                                                                                                Yours truly,

 

                                                                                                                                Erica M. Hamilton

 

cms

Enclosure

 


 

Appendix A

to Letter L-64-10

Page 1 of 1

 

 

FortisBC Inc.

2011 Capital Expenditure Plan

 

 

 

AMENDED REGULATORY TIMETABLE

 

 

 

                ACTION

DATE (2010)

FortisBC Workshop Registration with the Commission

Friday, July 30

FortisBC 2011 Capital Plan Workshop in Kelowna, BC

Wednesday, August 4

Registration of Interveners  and Interested Parties

Wednesday, August 11

Commission Information Request No. 1

Thursday, August 12

Intervener Participant Assistance Budgets

Friday, August 13

FortisBC Responses to Commission Information Request No. 1

Thursday, August 26

Commission Information Request No. 2 and
Intervener Information Requests No. 1

Friday, September 10

FortisBC Responses to Commission Information Request No. 2 and Intervener Information Requests No. 1

Wednesday, September 22

The Process for FortisBC’s Final Submission, Intervener Final Submissions, and FortisBC’s Reply Submission will be determined by the Commission at a later date.

 

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.