regulatory.affairs@terasengas.com January 8, 2010
|
TGW 2010 - 2011 Revenue Requirements and Rates Application Exhibit A-7 |
Mr. Tom Loski
Chief Regulatory Officer
Terasen Gas Inc.
16705 Fraser Highway
Surrey, BC V4N 0E8
Dear Mr. Loski:
Re: Terasen Gas (Whistler) Inc.
2010-2011 Revenue Requirements and Rate Application
Further to Commission Order Order G-136-09A and Letter L-113-09, the Commission Panel has approved Terasen Whistler’s request for an extension to the date for filing responses to information requests. An amended Regulatory Timetable is attached as Appendix A.
Yours truly,
Original signed by:
Constance M. Smith
for: Erica M. Hamilton
cms
Enclosure
cc: Registered Intervenors
APPENDIX A
to Letter L-4-10
Page 1 of 1
Terasen Gas (Whistler) Inc.
2010-2011 Revenue Requirements and Rate Application
PRELIMINARY REGULATORY TIMETABLE
ACTION DATES
Applicant Workshop Wednesday,
November 18, 2009
TGW to Publish Notice of the Application Friday, November 27, 2009
Commission Information Request No. 1 Wednesday, December 2, 2009
Intervenor Registration Friday, December 4, 2009
Intervenor Comments regarding Regulatory Process Friday, December 11, 2009
Commission Order setting out Regulatory Process Wednesday, December 16, 2009
Intervenor Information Request No. 1 Friday, December 18, 2009
TGW Response to Commission IR No. 1 Wednesday, December 23, 2009
TGW Response to Intervenor IR No. 1 Friday, January 15, 2010