Via Email
October 21, 2010
|
FortisBC – 2011 Capital Expenditure Plan Exhibit A-8 |
TO: Registered Interveners
FortisBC Inc.
Re: FortisBC Inc.
Project No. 3698603/Order G-112-10
Application for Approval of the 2011 Capital Expenditure Plan
The Commission writes to inform FortisBC and Interveners that an Oral Reply submission, as identified in the Amended Regulatory Timetable attached to Letter L-66-10 dated August 30, 2010, will not be required as the proceeding may conclude by way of a written Reply Submission by FortisBC on October 25, 2010.
Attached as Appendix A is a Revised Regulatory Timetable.
Yours truly,
Erica M. Hamilton
cms
Enclosure
APPENDIX A
to Letter L-87-10
Page 1 of 1
FortisBC Inc.
2011 Capital Expenditure Plan
REVISED REGULATORY TIMETABLE
ACTION |
DATE (2010) |
FortisBC Responses to Commission Information Request No. 2 and Intervener Information Requests No. 1 |
Friday, October 1, 2010 |
FortisBC Final Written Submission |
Friday, October 8, 2010 |
Intervener Final Written Submissions |
Monday, October 18, 2010 |
FortisBC Written Reply Submission |
Monday, October 25, 2010 |