cdonohue@png.ca                                                                                         February 23, 2011

 

 

PNG (N.E.)

2011 Revenue Requirements            Exhibit A-8

 

 

Mr. Craig P. Donohue

Director, Regulatory Affairs & Gas Supply

Pacific Northern Gas (N.E.) Ltd.

Suite 950

1185 West Georgia Street

Vancouver, BC   V6E 4E6

 

Dear Mr. Donohue:

 

Re:  Pacific Northern Gas (N.E.) Ltd.

Project No. 3698615/G-183-10

2011 Revenue Requirements Application

 

On February 22, 2011, Pacific Northern Gas (N.E.) Ltd. [PNG (N.E.)] filed a request with the Commission to amend PNG (N.E.)’s Regulatory Timetable as approved in Order G-9-11.  PNG (N.E.) has requested to extend the information response date from February 28, 2011 to March 7, 2011 and also recommended that the date for Interveners to comment on the regulatory process be extended to March 8, 2011.

 

The Interveners have confirmed their willingness to accommodate PNG (N.E.)’s request; thereby, the Commission approves PNG (N.E.)’s request and amends the Regulatory Timetable attached as Appendix A to this letter.

 

                                                                                                                                Yours truly,

 

 

 

                                                                                                                                Erica M. Hamilton

ac

Attachment

cc:   Registered Interveners

        (PNG(NE)-2011RR-RI)

 


Pacific Northern Gas (N.E.) Ltd.

Application for Approval of 2011 Amended Revenue Requirements

and Application for Consolidated Gas Sales Tariff

for Pacific Northern Gas (N.E.) Ltd. Service Area

 

 

 

AMENDED

REGULATORY TIMETABLE

 

 

 

ACTION

DATES (2011)

PNG (N.E.) Responses to Information Request No. 1

Monday, March 7

Intervener Comments regarding Regulatory Process

Tuesday, March 8

Information Request or Workshop No. 2 – pending

TBA

Commencement date for potential Negotiated Settlement Process

TBA

 