IN THE MATTER OF

The Utilities Commission Act, R.S.B.C. 1996, Chapter 473

 

and

 

FortisBC Energy Inc. and FortisBC Energy (Vancouver Island) Inc.

Energy Efficiency and Conservation Program

Natural Gas Vehicle Incentives Review

 

 

BEFORE:                 A.A. Rhodes, Panel Chair

                                D.A. Cote, Commissioner                                                    May 25, 2011

                                M.R. Harle, Commissioner

 

O  R  D  E  R

WHEREAS:

 

A.    On March 31, 2011, FortisBC Energy Inc. and FortisBC Energy (Vancouver Island) Inc. (FEI/FEVI, the Companies) submitted their Energy Efficiency and Conservation (EEC) Program 2010 Annual Report as a compliance filing in accordance with British Columbia Utilities Commission (Commission) Order G-36-09.  In the cover letter to the Report FEI/FEVI requests the Commission address the Companies’ use of EEC funds as incentives for Natural Gas Vehicles (NGVs) at the earliest possible date;

 

B.     On April 18, 2011, the Commission issued Letter L-30-11 which indicated the Commission would initiate a regulatory process to review and determine the appropriateness of the Companies’ use of EEC funds as NGV incentives;

 

C.     On April 20, 2011, the Commission issued Order G-70-11 establishing a Written Public Hearing process according to the Regulatory Timetable set out in Appendix A to that Order;

 

D.    The Commission has determined that changes to the Regulatory Timetable are required.

 

 

NOW THEREFORE the Commission orders the Written Public Hearing process for this matter is amended according to the Regulatory Timetable set out in Appendix A to this Order.

 

DATED at the City of Vancouver, in the Province of British Columbia, this         25th               day of May 2011.

 

                                                                                                                                BY ORDER

 

                                                                                                                            Original signed by:

 

A.A. Rhodes

Commissioner

Attachment

 

 

Appendix A

to Order G-96-11

Page 1 of 1

 

 

FortisBC Energy Inc. and FortisBC Energy (Vancouver Island) Inc.

Energy Efficiency and Conservation Program

Natural Gas Vehicle Incentives

 

 

AMENDED REGULATORY TIMETABLE

 

 

ACTION

DATE (2011)

Registration of Interveners and Interested Parties

Wednesday, April 27 

Commission and Intervener Information Request to FEI/FEVI

Wednesday, May 4

FEI/FEVI responds to Commission and Intervener Information Request

Tuesday, May 10

FEI/FEVI Final Submission

Thursday, May 12

Intervener Final Submissions

Friday, May 20

FEI/FEVI Reply Submission

Wednesday, May 25

Oral Argument, if necessary

Tuesday, June 21

 