Re: Commission Order G-36-11
Request for Extension to the Filing Date of Negotiated Rate
__________With Corix Multi-Utility Services Inc.____________
The British Columbia Utilities Commission (Commission) has received British Columbia Hydro and Power Authority’s (BC Hydro) letter dated May 19, 2011, which contains a request to extend the filing date of the negotiated rate with Corix Multi-Utility Services Inc. (Corix) from June 1, 2011, as ordered by Commission Order G-36-11, to August 31, 2011.
The Commission has also received a letter dated May 20, 2011 from Corix written in support of BC Hydro’s request and the Corix letter confirms that meetings have taken place and progress has been made but that it will not be possible to file a negotiated flat rate tariff by June 1, 2011.
The Commission Panel has reviewed both letters and has determined that it is reasonable to extend the date from June 1, 2011 to August 31, 2011.
Yours truly,
Alanna Gillis
EC/cms
cc: Mr. Ian Wigington
Corix Multi-Utility Services Inc.
Email: ian.wigington@corix.com
Mr. Ronald Cliff
Highcliff Energy Services Ltd.
Email: ron@highcliff.ca