Orders

Decision Information

Decision Content

IN THE MATTER OF

the Utilities Commission Act, R.S.B.C. 1996, Chapter 473

 

and

 

the Insurance Corporation Act, R.S.B.C. 1996, Chapter 228, as amended

 

and

Application for Participant Assistance/Cost Award

in the Insurance Corporation of British Columbia Application

for Approval of the Revenue Requirements for Universal Compulsory Automobile Insurance
for the Policy Year Commencing February 1, 2012

 

 

BEFORE:               A.W.K. Anderson, Panel Chair and Commissioner

                                M.R. Harle, Commissioner                                          

                                R.D. Revel, Commissioner                                            August 30, 2012               

 

 

O  R  D  E  R

WHEREAS:

 

A.      On December 1, 2011, the Insurance Corporation of British Columbia (ICBC) submitted an application to the British Columbia Utilities Commission (Commission) for approval of the Revenue Requirements for Universal Compulsory Automobile Insurance (Basic Insurance) for the policy year commencing February 1, 2012 (the Application);

 

B.      By Order G-21-12 dated February 29, 2012, subsequent to a Pre-hearing Conference, the Commission established a Revised Regulatory including: (i) an Oral Public Hearing for actuarial matters only and (ii) ICBC and Intervener Oral Final Arguments, and ICBC Oral Reply Argument;

 

C.      By Order G-62-12 dated May 22, 2012, subsequent to comments received from ICBC and four Interveners regarding the necessity of a limited Oral Public Hearing on actuarial matters only, and potentially replacing the oral argument process with written arguments, the Commission established an Amended Regulatory Timetable for the remaining regulatory process. The Amended Regulatory Timetable replaced both the limited Oral Public Hearing on actuarial matters and the oral argument process with a full written process;

 

D.      By Order G-109-12 with Decision issued concurrently, the Commission approved the Application’s requested 11.2 percent increase in Basic Insurance rates for the Policy Year 2012, commencing February 1, 2012;

 

E.       By letter dated July 19, 2012, the British Columbia Public Interest Advocacy Centre filed with the Commission a Participant Assistance/Cost Award (PACA) on behalf of its client, the British Columbia Old Age Pensioners’ Organization et al. (BCOAPO) with respect to its participation in the 2012 ICBC Revenue Requirements proceeding for the total amount of $33,610.56;

 

F.       By letter dated August 7, 2012, ICBC indicated it had no comments on the BCOAPO PACA Application;

 

G.     The Commission has reviewed the BCOAPO PACA Application with regard to the criteria and rates set out in the PACA Guidelines in Commission Order G‑72-07 and concluded that cost award should be approved for the amount set out in the BCOAPO PACA Application.

 

 

NOW THEREFORE pursuant to sections 118(1) of the Utilities Commission Act, the Commission orders as follows:

 

1.       Approval of cost award for the BCOAPO in the amount of $33,610.56 for its participation in the 2012 ICBC Revenue Requirements proceeding.

 

2.       ICBC is directed to reimburse the above-noted participant in a timely manner.

 

 

DATED at the City of Vancouver, in the Province of British Columbia, this            30th           day of August 2012.

 

                                                                                                                              BY ORDER

 

Original signed by:

 

                                                                                                                              A.W.K. Anderson

                                                                                                                              Panel Chair and Commissioner

 

 


 