IN THE MATTER OF
the Utilities Commission Act, R.S.B.C. 1996, Chapter 473
and
FortisBC Inc.
Application for a Certificate of Public Convenience and Necessity
for the Advanced Metering Infrastructure Project
BEFORE: L.F. Kelsey, Commissioner
D.M. Morton, Commissioner September 13, 2012
N.E. MacMurchy, Commissioner
O R D E R
WHEREAS:
A. On July 26, 2012, FortisBC Inc. (FortisBC) applied to the British Columbia Utilities Commission, pursuant to sections 45, 46, and 56 of the Utilities Commission Act (the Act), for approval of the Advanced Metering Infrastructure (AMI) Project (Project), including approval of a revised depreciation rate for the proposed meters to be installed (the Application);
B. On August 2, 2012, the Commission established a Preliminary Regulatory Timetable, attached as Appendix A to the Order G-105-12;
C. The Commission acknowledges the delay that has been caused as a result of the need to evaluate the requests for Registered Intervener status and requests for additional time for Interveners to prepare submissions. For these reasons, the Commission determines it is necessary to amend the Preliminary Regulatory Timetable to review the Application.
NOW THEREFORE the Commission orders as follows:
1. The Commission amends the Preliminary Regulatory Timetable, attached as Appendix A to the Order.
2. FortisBC will distribute copies of this Order and its Appendix A, in a timely fashion, via email, to the Registered Interveners and Interested Parties in the proceeding.
3. Any party intending to file for a Participant Assistance Cost Award (PACA) must submit its PACA budget, pursuant to the PACA Guidelines attached to Order G-72-07, to the Commission by Tuesday, October 2, 2012. (A complete description of the PACA Guidelines is available at the Commission’s web site:
http://www.bcuc.com/Documents/Guidelines/Participant_Guide.pdf )
DATED at the City of Vancouver, in the Province of British Columbia, this 13th day of September 2012.
BY ORDER
Original signed by:
L.F. Kelsey
Commissioner
Attachment
FortisBC Inc.
Application for a Certificate of Public Convenience and Necessity
for the Advanced Metering Infrastructure Project
Amended PRELIMINARY
REGULATORY TIMETABLE
ACTION |
DATE (2012) |
Comments on the need to hold Community Input Sessions in the areas of Trail, Osoyoos, and Kelowna |
Friday, September 14 |
Finalization of Registration of Interveners and Interested Parties |
Friday, September 14 |
BCUC Information Request No. 1 |
Friday, September 14 |
FortisBC reply on the need to hold Community Input Sessions in the areas of Trail, Osoyoos, and Kelowna |
Wednesday, September 19 |
Comments by Registered Interveners on the regulatory process by which to review the Application, such as written, oral or both |
Friday, September 21 |
Commission Decision on the need to hold Community Input Sessions in the areas of Trail, Osoyoos, and Kelowna |
Friday, September 21 |
Commission Decision on the regulatory process by which to review the Application, such as written, oral or both |
Tuesday, September 25 |
Participants file their PACA Funding Budgets |
Tuesday, October 2 |
FortisBC Response to BCUC Information Request No. 1 |
Friday, October 5 |
Intervener Information Request No. 1 |
Friday, October 26 |
Week of November 5th for Community Input Sessions, if they are to be held |
|
FortisBC Response to Intervener Information Request No. 1 |
Friday, November 9 |
BCUC and Intervener Information Request No. 2 |
Friday, November 23 |
FortisBC Response to BCUC and Intervener Information Request No. 2 |
Friday, December 14 |