                                                                                                                                September 13, 2012

 

 

 

British Columbia Utilities Commission

Generic Cost of Capital Proceeding     Exhibit A-16

 

 

To:          All Registered Parties

                (BCUC-GCOC)

 

 

Re:  British Columbia Utilities Commission

Project No. 3698659/G-20-12

Generic Cost of Capital Proceeding

Amended Preliminary Regulatory Timetable

 

The Procedural Conference that was scheduled to occur on October 2, 2012 by Commission Order G-84-12 has been rescheduled to take place on October 4, 2012 commencing at 9:00 a.m. in the Commission’s Hearing Room, Twelfth Floor, 1125 Howe Street, Vancouver, BC.

 

Please find enclosed an Amended Preliminary Regulatory Timetable attached as Appendix A with the amendment in bold.

 

                                                                                                                                Yours truly,

 

                                                                                                                                Erica Hamilton

/yl

Attachment

 


 

 

 

 

 

GENERIC COST OF CAPITAL PROCEEDING

 

AMENDED

PRELIMINARY REGULATORY TIMETABLE

 

 

 

ACTIVITY

DATE (2012)

Response to IR No. 1 from Affected and Other Utilities

Monday, Sept 24

Procedural Conference

Thursday, October 4

Commission and Interveners’ IR No 2 on Affected and Other Utilities’ Evidence

Tuesday, October 9

Response to IR No. 2 from Affected and Other Utilities

Monday, October 29

Intervener Evidence

Monday, November 5

IR No. 1 on Intervener Evidence

Friday, November 16

Response to IR No. 1 on Intervener Evidence

Friday, November 30

Rebuttal Evidence

Oral Hearing, if any

Thursday, December 6

Wednesday, December 12

 

 

 

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.