IN THE MATTER OF
the Utilities Commission Act, R.S.B.C. 1996, Chapter 473
and
An Application by FortisBC Inc.
for Acceptance of a Mitigation Plan required for Compliance with Mandatory Reliability Standard
PRC-017-0 Requirement 1 - Violation ID: BCUC201200356
BEFORE: L.F. Kelsey, Commissioner
B.A. Magnan, Commissioner October 25, 2012
O R D E R
WHEREAS:
A. Section 125.2 of the Utilities Commission Act (Act) assigns exclusive jurisdiction to the British Columbia Utilities Commission (Commission) to determine whether a “reliability standard,” as defined in the Act, is in the public interest and should be adopted in British Columbia. By Order G-123-09 the Commission approved the Compliance Monitoring Program (CMP) for monitoring and enforcement of adopted reliability standards and appointed the Western Electricity Coordinating Council (WECC) as its Administrator for registration and monitoring compliance as per section 8 of the Act;
B. Commission Order G-67-09 requires entities subject to approved Mandatory Reliability Standards to file mitigation plans outlining how they plan to achieve compliance;
C. Pursuant to Section 5.3 of the CMP, a Mitigation Plan with respect to an Alleged Violation may be submitted at any time, and a Mitigation Plan with respect to a Confirmed Violation must be submitted within ten business days following confirmation by the Commission;
D. On March 14, 2012, FortisBC submitted a Mitigation Plan to address the alleged violation of Reliability Standard PRC-017-0 R1. The proposed completion date for the Mitigation Plan is July 25, 2013;
E. By letter dated June 15, 2012, WECC recommended acceptance of the following Mitigation Plan to bring FortisBC into compliance with the standard identified below:
Reliability Standard |
BCUC Violation ID |
Completion Date |
PRC-017-0 R1 |
BCUC201200356 |
July 25, 2013 |
F. The Commission reviewed WECC’s recommendation and considers approval is warranted.
NOW THEREFORE pursuant to section 125.2 (10) of the Act and in accordance with the Compliance Monitoring Program, the Commission accepts WECC’s recommendation and approves the Mitigation Plan as listed above.
DATED at the City of Vancouver, in the Province of British Columbia, this 29th day of October 2012.
BY ORDER
Original signed by:
L.F. Kelsey
Commissioner