IN THE MATTER OF
the Utilities Commission Act, R.S.B.C. 1996, Chapter 473
and
An Application by British Columbia Hydro and Power Authority
for Acceptance of Mitigation Plans required for Compliance with Mandatory Reliability Standards
PRC-011-0 Requirement 1 - Violation ID: BCUC201000009
PRC-011-0 Requirement 2 - Violation ID: BCUC201200359
BEFORE: D.M. Morton, Commissioner April 24, 2013
O R D E R
WHEREAS:
A. Section 125.2 of the Utilities Commission Act (Act) assigns exclusive jurisdiction to the British Columbia Utilities Commission (Commission) to determine whether a “reliability standard,” as defined in the Act, is in the public interest and should be adopted in British Columbia. By Order G-123-09, the Commission approved the Compliance Monitoring Program (CMP) for monitoring and enforcement of adopted reliability standards and appointed the Western Electricity Coordinating Council (WECC) as its Administrator for registration and monitoring compliance as per section 8 of the Act;
B. Commission Order G-67-09 requires entities subject to approved Mandatory Reliability Standards to file mitigation plans outlining how they plan to achieve compliance;
C. Pursuant to Section 5.3 of the CMP, a Mitigation Plan with respect to an Alleged Violation may be submitted at any time, and a Mitigation Plan with respect to a Confirmed Violation must be submitted within ten business days following confirmation by the Commission;
D. On March 7, 2012, British Columbia Hydro and Power Authority (BC Hydro) submitted a Mitigation Plan to address the alleged violation of Reliability Standard PRC-011-0 R1. WECC rejected the Mitigation Plan on October 29, 2012;
E. On December 17, 2012, BC Hydro submitted Mitigation Plans to address the alleged violation of Reliability Standards PRC-011-0 R1 and R2. The proposed completion date for both Mitigation Plans is May 30, 2014;
F. By letters dated April 18, 2013, WECC recommended acceptance of the following Mitigation Plans to bring BC Hydro into compliance with the standards identified below:
Reliability Standard |
BCUC Violation ID |
Completion Date |
PRC-011-0 R1 |
BCUC201000009 |
May 30, 2014 |
PRC-011-0 R2 |
BCUC201200359 |
May 30, 2014 |
G. By letters dated April 18, 2013, WECC also stated that the duration of both Mitigation Plans is longer than WECC would generally recommend for PRC-011-0 violations of similar scope. For this reason, WECC recommends, that the Commission should hold BC Hydro to the proposed completion date of May 30, 2014;
H. The Commission has reviewed WECC’s recommendations and considers approval is warranted.
NOW THEREFORE pursuant to section 125.2 (10) of the Act and in accordance with the Compliance Monitoring Program, the Commission accepts WECC’s recommendation and approves the Mitigation Plans with the completion date as identified above.
DATED at the City of Vancouver, in the Province of British Columbia, this 24th day of April 2013.
BY ORDER
Original signed by:
D.M. Morton
Commissioner