IN THE MATTER OF

the Utilities Commission Act, R.S.B.C. 1996, Chapter 473

 

and

 

An Application by FortisBC Energy Inc.

for Approval to Extend the Maturity Date of Indebtedness Under

the Term Credit Agreement

 

 

BEFORE:               L.F. Kelsey, Commissioner

                                C.A. Brown, Commissioner                                          June 13, 2013

                                N.E. MacMurchy, Commissioner

                                B.A. Magnan, Commissioner

                                D.M. Morton, Commissioner

                                C. van Wermeskerken, Commissioner

 

 

O  R  D  E  R

WHEREAS:

A.      On May 30, 2013, FortisBC Energy Inc. (FEI) applied to the British Columbia Utilities Commission (Commission), pursuant to sections 50(2) and 50(3) of the Utilities Commission Act, for an extension of its term credit facility for a further 365 days, from the current maturity date of August 24, 2014, to an extended maturity date of August 24, 2015 (Application);

B.      Pursuant to Commission Order G-96-07 dated August 14, 2007, the Commission approved the incurrence of indebtedness by FEI (then Terasen Gas Inc.) under a credit agreement between FEI, the Canadian Imperial Bank of Commerce (CIBC) and other lenders, and CIBC as administrative agent for the lenders, providing for an unsecured revolving term credit facility for the principal amount of up to $500 million with an initial term not to exceed five years (Term Credit Agreement);

C.      The Term Credit Agreement entered into on August 24, 2007, has an annual extension mechanism that permits FEI to request the lenders to extend the then current maturity date of the Term Credit Agreement for a further 365 days;

D.      By Orders G-90-08 and G-78-12, the Commission approved 365 day extensions of the maturity date under the Term Credit Agreement to August 24, 2013 and August 24, 2014, respectively;

E.       The Commission reviewed the Application and finds that approval is warranted.

 

 

NOW THEREFORE pursuant to sections 50(2) and 50(3) of the Utilities Commission Act, the Commission orders as follows:

 

1.       FortisBC Energy Inc.’s application to extend the current maturity date under the Term Credit Agreement for a further 365 days is approved.

 

2.       FortisBC Energy Inc. must file with the Commission the updated Term Sheet which will disclose the upfront amendment fee for the extended term as granted by the lenders.

 

 

DATED at the City of Vancouver, In the Province of British Columbia, this           13th               day of June 2013.

 

                                                                                                                                BY ORDER

 

Original Signed By:

 

D.M. Morton

Commissioner

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.