Via Email

jkennedy@png.ca                                                                                                February 27, 2013

 

 

PNG-PNG (ne) 2012 Pension &

Non-Pension Benefits                        Exhibit A-4

 

Ms. Janet P. Kennedy

Vice-President, Regulatory Affairs & Gas Supply

Pacific Northern Gas Ltd.

1185 West Georgia Street

Suite 950

Vancouver, BC   V6E 4E6

 

Dear Ms. Kennedy:

 

Re:  An Application by Pacific Northern Gas Ltd.

and Pacific Northern Gas (N.E.) Ltd. (PNG Consolidated)

for 2012 Pension and Non-Pension Benefits

 

British Columbia Utilities Commission (Commission) Order G-196-12 established a Regulatory Timetable for the review of the PNG Consolidated Application for 2012 Pension and Non-Pension Benefits.

 

On February 26, 2013, PNG filed a letter requesting a variance to the Regulatory Timetable and proposed revised deadlines for information requests, information responses and argument submissions.  On February 26, 2013, the British Columbia Pensioners’ and Seniors’ Organization, Active Support Against Poverty, BC Coalition of People with Disabilities, Counsel of Senior Citizens’ Organizations of BC, and the Tenant Resource and Advisory Centre (collectively the BCPSO et al.), a registered intervener in this proceeding filed an email in support of PNG’s proposed revisions to the Regulatory Timetable.

 

The Commission Panel has reviewed PNG’s request and the BCPSO’s comment and issues the Amended Regulatory Timetable that is attached as Appendix A. 

 

                                                                                                                                Yours truly,

 

                                                                                                                                Erica Hamilton

PWN/cms

Enclosure

 


 

 

 

Pacific Northern Gas Ltd. and

Pacific Northern Gas (N.E.) Ltd. (PNG Consolidated)

2012 Pension and Non-Pension Benefits Application

 

 

 

AMENDED REGULATORY TIMETABLE

 

 

 

ACTION

DATE (2013)

PNG Responses to Commission Information Request No. 1

Friday, March 8

PNG Responses to Intervener Information Request No. 1

Friday, March 8

Commission and Intervener Information Request No. 2

Friday, March 22

PNG Responses to Commission and Intervener Information Request No. 2

Friday, April 5

PNG Final Argument Submissions

Friday, April 12

Intervener Final Argument Submissions

Friday, April 19

PNG Reply Submissions

Friday, April 26

 

 

 