Orders

Decision Information

Decision Content

Via Email                                                                                                             

gas.regulatory.affairs@fortisbc.com                                                       December 19, 2011

 

 

Ms. Diane Roy

Director, Regulatory Affairs - Gas

FortisBC Energy Inc.

16705 Fraser Highway

Surrey, BC   V4N 0E8

 

Dear Ms. Roy:

Re:  FortisBC Energy Inc.

and FortisBC Energy (Vancouver Island) Inc.

Request to Extend Filing Deadline for the 2012/13 Annual Contracting Plans

 

In British Columbia Utilities Commission (Commission) Letter L-69-11, dated September 1, 2011, the Commission accepted the FortisBC Energy Inc. (FEI) 2011/12 Annual Contracting Plan (ACP) and directed FEI to file the 2012/2013 FEI ACP by April 1, 2012.

 

In Commission Letter L-74-11, dated September 19, 2011, the Commission accepted the FortisBC Energy (Vancouver Island) Inc. (FEVI) 2011/12 Annual Contracting Plan (ACP) and directed FEVI to file the 2012/2013 FEVI ACP by April 1, 2012.

 

Further to your December 13, 2011 request to extend the 2012/2013 ACP filing deadline to May 1, 2012 for both the FEI and FEVI 2012/2013 ACPs, please be advised that the Commission approves the requested filing deadline extension.

 

                                                                                                                                Yours truly,

 

 

 

                                                                                                                                Alanna Gillis

CM/elm

 

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.