Orders

Decision Information

Decision Content

IN THE MATTER OF

the Utilities Commission Act, R.S.B.C. 1996, Chapter 473

 

and

 

Rio Tinto Alcan

Confirmation of Alleged Violation of Mandatory Reliability Standards:

FAC-003-1 Requirement 1 – Violation ID:  BCUC2013000416

FAC-003-1 Requirement 2 – Violation ID:  BCUC2013000417

 

 

BEFORE:               D.M. Morton, Commissioner                                      July 3, 2014

 

 

O  R  D  E  R

 

WHEREAS:

A.      Order G-123-09 approved the Compliance Monitoring Program (CMP) which provides a process for dealing with violations to Mandatory Reliability Standards (MRS) adopted by the British Columbia Utilities Commission (Commission);

 

B.      On May 19, 2014, the Western Electricity Coordinating Council (WECC), acting as the Commission’s MRS Administrator, issued a Notice of Alleged Violation (NOAV) to Rio Tinto Alcan (Rio Tinto) for the alleged violation of the Reliability Standards listed above.  The NOAV described the nature of the Alleged Violations and provided an assessment of the severity of the Alleged Violations;

 

C.      On May 19, 2014, WECC also advised Rio Tinto of its rights under section 4.2 of the CMP, pursuant to which the Applicable Entity has 30 days to respond to the NOAV.  The CMP also states if the Applicable Entity fails to respond within 30 days, the Commission may consider the Alleged Violations in the absence of a submission;

 

D.      By email correspondence dated June 26, 2014, WECC informed Commission staff that Rio Tinto accepts the Alleged Violations noted above;

 

E.       Pursuant to section 5.1.1 of the CMP, the Applicable Entity is not required to, but may, prepare a Mitigation Plan for an Alleged Violation at any time.  Pursuant to section 5.3.2 of the CMP, the Applicable Entity must submit a Mitigation Plan for a Confirmed Violation within ten business days following confirmation by the Commission;


 

F.       By Commission Order R-26-13, dated June 20, 2013, the Commission accepted Mitigation Plans submitted by Rio Tinto for these Alleged Violations, both with a proposed completion date of May 29, 2014;

 

G.     The Commission has reviewed WECC’s recommendation and considers confirmation of the Alleged Violations is warranted.

 

 

NOW THEREFORE pursuant to section 125.2 of the Utilities Commission Act and section 4.1 of the Compliance

Monitoring Program, the British Columbia Utilities Commission confirms the Alleged Violations identified above. 

 

 

DATED at the City of Vancouver, in the Province of British Columbia, this                  4th                    day of July 2014.

 

                                                                                                                                BY ORDER

 

Original Signed by:

 

                                                                                                                                D.M. Morton

                                                                                                                                Commissioner