IN THE MATTER OF

the Utilities Commission Act, RSBC 1996, Chapter 473

 

and

 

British Columbia Hydro and Power Authority

Application for Approval of Shore Power Rate

Rate Schedules 1280, 1891 and Shore Power Service Agreement

Electric Tariff Supplement No. 86

 

BEFORE:               N. E. MacMurchy, Panel Chair

                                K. A. Keilty, Commissioner                                           April 15, 2015

                                B. A. Magnan, Commissioner

 

 

O R D E R

WHEREAS:

 

A.      By Order G-197-08 dated December 18, 2008, the British Columbia Utilities Commission (Commission) approved a BC Hydro shore service rate, Electric Tariff Supplement (TS) 76, for the provision of non-firm shore service for use by Port Metro Vancouver for cruise ships to Canada Place Wharf. Order G-197-08 was issued pursuant to a ministerial order to the Commission BC Reg. 291/2008;

B.      On January 28, 2015, BC Hydro held a shore power rate workshop to present to stakeholders its proposed new shore power rate that would expand the eligibility criteria stipulated in TS 76;

C.      By letter dated April 10, 2015, BC Hydro filed its application for approval of Rate Schedules 1280 and 1891, and TS 86 for the provision of non-firm shore power service (Application). The Application is in response to requests from Port Metro Vancouver and Prince Rupert Port Authority and is based on the previously Commission approved TS 76, and expands port customer and vessel eligibility; and

D.      The Panel has considered BC Hydro’s Application and proposed regulatory review process.

 

NOW THEREFORE, the Commission orders, pursuant to section 61 of the Utilities Commission Act, that a regulatory proceeding be established for the review of the Shore Power Rate Application in accordance with the regulatory timetable that is set out and attached as Appendix A to this order.

 

 

DATED at the City of Vancouver, in the Province of British Columbia, this      15th        day of April 2015

 

                                                                                                                                BY ORDER

 

                                                                                                                            Original signed by:

 

                                                                                                                                N. E. MacMurchy

                                                                                                                                Panel Chair / Commissioner

Attachment

 


 

British Columbia Hydro and Power Authority

Application for Approval of Shore Power Rate

Rate Schedules 1280, 1891 and Shore Power Service Agreement

Electric Tariff Supplement No. 86

 

 

REGULATORY TIMETABLE

 

ACTION

DATE (2015)

Intervener registration deadline

Tuesday, April 21

Commission IR No. 1

Friday, April 24

Intervener IR No. 1

Monday, April 27

BC Hydro Response to Commission and Intervener IR No. 1

Friday, May 15

BC Hydro submission on suitability of SRP/need for further review process

Tuesday, May 19

Intervener submissions on suitability of SRP/need for further review process

Tuesday, May 26

Proposed date of SRP, if needed

Thursday, June 11

 

 

 