IN THE MATTER OF
the Utilities Commission Act, RSBC 1996, Chapter 473
and
British Columbia Hydro and Power Authority
Application for Approval of Contracted Generator
Baseline Guidelines
and Reconsideration and Variance of Order G-19-14
BEFORE: L. A. O’Hara, Panel Chair/Commissioner
R. D. Revel, Commissioner April 23, 2015
B. A. Magnan, Commissioner
O R D E R
WHEREAS:
A. On November 2, 2012, British Columbia Hydro and Power Authority (BC Hydro) filed an application with the British Columbia Utilities Commission (Commission) for Approval to Amend Tariff Supplement No. 74 Customer Baseline Load Determination Guidelines for Rate Schedule 1823 Customers with Self-Generation Facilities (TS 74 Application);
B.
The proposed amendments
to TS 74 impacted GBLs for customers with contracted generating units
(Contracted GBLs); however, the principles for setting Contracted GBLs were not
addressed as part of the
TS 74 Application. In that proceeding, BC Hydro stated that BC Hydro and the
customer negotiate Contracted GBLs in accordance with the principles set out in
the 2012 GBL Information Report;
C. On February 17, 2014, by Order G-19-14, the Commission made its final determination on the TS 74 Application and, pursuant to Directive 2, directed BC Hydro to file an application with the Commission for approval of updated GBL Guidelines to be incorporated into TS 74;
D.
On May 21, 2014, BC
Hydro applied to the Commission for a reconsideration and variance of Order
G-19-14 requesting that the Commission rescind Directive 2 (Phase 1
Reconsideration Application). By Order
G-106-14, dated July 25, 2014, the Commission denied BC Hydro’s application to
rescind Directive 2 as it related to BC Hydro’s requirement to file an
application with the Commission for approval of updated Contracted GBL
Guidelines. However, the Commission accepted that there may be alternatives to
filing the Contracted GBL Guidelines other than incorporating them into TS 74
and established Phase Two to reconsider Order G-106-14 as it relates to where
the Contracted GBL Guidelines should reside (Phase 2 Reconsideration);
E.
On December 12, 2014,
BC Hydro filed its application for approval of Contracted GBL Guidelines in
compliance with Order G-19-14 and the Phase 2 Reconsideration and Variance
established by Order
G-106-14 (Application);
F. In the cover letter to the Application, BC Hydro proposes a regulatory process and timetable consisting of one round of information requests (IRs) followed by a streamline review process. On December 16, 2014, the Commission issued Order G-199-14, establishing an initial regulatory timetable for the review of the Application which included, among other things, one round IRs and submissions from the parties on further regulatory process;
G. The British Columbia Old Age Pensioners’ Organization et al., B.C. Sustainable Energy Association and Sierra Club of British Columbia, Commercial Energy Consumers Association of British Columbia, FortisBC Inc., Zellstoff Celgar Limited Partnership, the Association of Major Power Customers and West Fraser Mills registered as interveners;
H. By Order G-12-15, the Commission established that a procedural conference would take place on Thursday, February 5, 2015, and also suspended the Regulatory Timetable established by Order G-199-14;
I. On February 12, 2015, by Order G-18-15, after considering submission made at the procedural conference, the Commission, among other things, found that the establishment of an issues list to guide the parties is preparing their information requests (IRs) would be an efficient step and sought submission on a Panel General Issues List;
J. By Order G-42-15 the Commission considered the submissions and established a Panel General Issues List, lifted the suspension to Order G-199-14 and established a regulatory timetable for information requests and responses and submissions on further process.
K. On April 17, 2015, BC Hydro requested an amendment to the Regulatory Timetable established by Order G-42-15 to extend the date for filing its responses to the Commission staff and intervener information requests; and
L. The Commission reviewed BC Hydro’s request and considers that an amendment to the Regulatory Timetable is required.
NOW THEREFORE the Commission orders as follows:
1. The revised Regulatory Timetable for the review of the Application is set out in Appendix A to this order.
DATED at the City of Vancouver, in the Province of British Columbia, this 23rd day of April 2015.
BY ORDER
Original signed by:
L. A. O’Hara
Panel Chair/Commissioner
Attachment
British Columbia Hydro and Power Authority
Application for Approval of Contracted Generator
Baseline Guidelines
and Reconsideration and Variance of Order G-19-14
REGULATORY TIMETABLE
ACTION |
DATE (2015) |
BC Hydro Responses to Information Request No. 1 |
Monday, May 11 |
Intervener Submissions on Further Process |
Tuesday, May 19 |
BC Hydro Reply to Intervener Submissions of Further Process |
Monday, May 25 |