Via Email                                                                                                              September 10, 2015

jkennedy@png.ca

 

 

Ms. Janet P. Kennedy

Vice-President, Regulatory Affairs & Gas Supply

Pacific Northern Gas Ltd.

950, 1185 West Georgia Street

Vancouver, BC   V6E 4E6

 

Dear Ms. Kennedy:

Re:  Pacific Northern Gas (N.E.) Ltd.

2015 Third Quarter Report on Gas Supply Costs for the

Fort St. John/Dawson Creek and Tumbler Ridge Service Areas

 

On August 28, 2015, Pacific Northern Gas (N.E.) Ltd. [PNG (N.E.)] filed with the British Columbia Utilities Commission (Commission) its Third Quarter 2015 Report on gas supply costs and Gas Cost Variance Account (GCVA) balances for its Fort St. John/Dawson Creek (FSJ/DC) and Tumbler Ridge (TR) service areas (Report).

 

The Commission, by Letters L-5-01 and L-40-11, set out a guideline trigger mechanism and rate change methodology (Guidelines) that have generally been adopted by natural gas and propane utilities including
PNG (N.E.).

 

For FSJ/DC and TR, the Commission notes that Order G-45-15 established the current gas commodity rates, GCVA commodity rate rider, and Company Use GCVA gas cost rate rider. These rates and related riders were maintained through Letter L-24-15. Order G-194-14 established the current Company Use gas cost delivery rate and Company Use gas commodity price used for deferral accounting.

 

The Commission reviewed the Report taking into account the Guidelines and accepts PNG (N.E.)’s recommendations that no changes to the gas commodity rates and gas cost rate riders are required for FSJ/DC and TR. The rates established under the above noted orders will remain unchanged at October 1, 2015.

 

                                                                                                                                Yours truly,

 

                                                                                                                                Erica Hamilton

ES/dg


cc:           Mr. Verlon G. Otto, CPA, CA

                Manager, Regulatory Affairs & Special Projects

                Pacific Northern Gas Ltd.

                votto@png.ca

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.