Orders

Decision Information

Decision Content

IN THE MATTER OF

the Utilities Commission Act, RSBC 1996, Chapter 473

 

and

 

FortisBC Energy Inc.

2015 System Extension Application

 

 

BEFORE:               K. A. Keilty, Panel Chair/Commissioner

                                I. F. MacPhail, Commissioner                                      September 1, 2015

                                D. M. Morton, Commissioner

 

 

O  R  D  E  R

WHEREAS:

 

A.      On June 30, 2015, FortisBC Energy Inc. (FEI) applied to the British Columbia Utilities Commission (Commission) for approval of changes to its Mains Extension Test (MX Test), Customer Connection Policy and related reporting requirements (Application);

B.      On July 23, 2015, the Commission issued Order G-126-15, establishing a regulatory timetable for the review of the Application;

C.      On August 31, 2015, FEI submitted a letter to the Commission with copy to registered participants requesting to extend the regulatory timetable by three weeks to file responses to Commission and Intervener Information Request No. 1 on September 25, 2015 instead of September 4, 2015. FEI requested an extension due to resource constraints from multiple deadlines in other ongoing regulatory processes;

D.      Commercial Energy Consumers Association of BC, British Columbia Hydro and Power Authority, BC Old Age Pensioners’ Organizations et al., and the BC Sustainable Energy Association and the Sierra Club of British Columbia submitted letters to the Commission stating no objection to the extension request; and

E.       The Panel has considered the request and comments received and agrees that granting an extension is warranted.

 

NOW THEREFORE the British Columbia Utilities Commission orders as follows:

 

1.       The amended Regulatory Timetable for the review of the Application is set out in Appendix A to this order.

 

DATED at the City of Vancouver, in the Province of British Columbia, this          1st          day of September 2015.

 

                                                                                                                                BY ORDER

 

Original signed by:

 

K. A. Keilty

                                                                                                                                Commissioner

 

Attachment

 


FortisBC Energy Inc.

2015 System Extension Application

 

 

REGULATORY TIMETABLE

 

ACTION

DATE (2015)

FEI Response to Commission and Intervener Information Request No. 1

Friday, October 2

Intervener and FEI Submissions on Further Process

Friday, October 9

FEI Reply to Intervener Submissions on Further Process

Wednesday, October 14

Further Process

To Be Determined

 

 

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.