ORDER NUMBER
R-21-16
IN THE MATTER OF
the Utilities Commission Act, RSBC 1996, Chapter 473
and
Catalyst Paper Crofton Division
Application for Acceptance of a Mitigation Plan (Version 2) required for
Compliance with Mandatory Reliability Standard:
PRC-017-0 Requirement 2 - Violation ID: BCUC2014000492
BEFORE:
D. M. Morton, Commissioner
on May 26, 2016
ORDER
WHEREAS:
A. Section 125.2 of the Utilities Commission Act (UCA) assigns exclusive jurisdiction to the British Columbia Utilities Commission (Commission) to determine whether a “reliability standard,” as defined in the UCA, is in the public interest and should be adopted in British Columbia. By Order G-123-09, the Commission approved the Compliance Monitoring Program (CMP) for monitoring and enforcement of adopted reliability standards and appointed the Western Electricity Coordinating Council (WECC) as its Administrator for registration and monitoring compliance as per section 8 of the UCA. WECC’s role as Administrator for the BC Mandatory Reliability Standards (MRS) Program was renewed in the first amended Administration Agreement, dated August 21, 2014. The CMP was revised and updated by Commission Order R-34-15, dated June 3, 2015;
B. Pursuant to section 5 of the CMP, an entity subject to approved Mandatory Reliability Standards found in Confirmed Violation of a reliability standard must prepare a Mitigation Plan (MP) to correct the Confirmed Violation or prepare a description of how the Confirmed Violation has been mitigated. An MP with respect to a Confirmed Violation must be submitted to the Administrator within ten days following confirmation by the Commission;
C. An MP with respect to an Alleged Violation may be submitted at any time and the Commission encourages entities to mitigate all perceived instances of noncompliance upon detection;
D. By Commission Order R-47-14, dated September 23, 2014, the Commission confirmed the Alleged Violation PRC-017-0 R2 for Catalyst Paper Crofton Division (CPCD);
E. On October 6, 2014, CPCD submitted an MP to address the Confirmed Violation noted above with the proposed completion date of February 3, 2015, and on March 3, 2016, CPCD submitted MP (Version 2) with the same proposed completion date to more fully address this Confirmed Violation;
F. By email notification dated May 13, 2016, WECC recommended acceptance of the following MP to bring CPCD into compliance with the Reliability Standard identified below:
Confirmed Violation |
BCUC Violation ID |
Date MP (Version 2) Submitted to WECC |
Proposed Completion Date |
PRC-017-0 R2 |
BCUC2014000492 |
March 3, 2016 |
February 3, 2015 |
G. The Commission reviewed WECC’s recommendation and considers acceptance is warranted.
NOW THEREFORE pursuant to section 125.2(10) of the Utilities Commission Act and in accordance with the Compliance Monitoring Program, the British Columbia Utilities Commission accepts the Mitigation Plan (Version 2) with the completion date as identified above.
DATED at the City of Vancouver, in the Province of British Columbia, this 26th day of May 2016.
BY ORDER
Original Signed By:
D. M. Morton
Commissioner