ORDER NUMBER

G-110-16

 

IN THE MATTER OF

the Utilities Commission Act, RSBC 1996, Chapter 473

 

and

 

Sun Peaks Utilities Co., Ltd.

Application for Approval of a Delivery Rate Increase

 

BEFORE:

D. M. Morton, Commissioner

 

on July 13, 2016

 

ORDER

WHEREAS:

 

A.       On June 13, 2016, Sun Peaks Utilities Co., Ltd. (SPUCL) filed an application with the British Columbia Utilities Commission (Commission) for approval of an increase of $0.33 per gigajoule in the Gas Delivery Charge effective August 1, 2016, for all Rate Groups (Residential, Small Commercial and Large Commercial) (Application);

B.       The proposed change will have an average annual impact of 1.3 percent increase for small residential customers and a 2.2 percent increase for small and large commercial customers;

C.       On June 30, 2016, the Commission issued Order G-102-16 approving the rate increase on an interim and refundable basis, and established the regulatory timetable for the review of the Application;

D.       On July 12, 2016, SPUCL filed a request with the Commission seeking an extension to the regulatory timetable in order to provide sufficient notice to its customers; and

E.        The Commission has considered the extension request and agrees that adequate public notice is necessary.

 

NOW THEREFORE the British Columbia Utilities Commission orders as follows:

 

1.       The Regulatory Timetable is amended as in Appendix A to this order.

2.       Sun Peaks Utilities Co., Ltd. is directed to provide notice of the Application and this order to affected customers by Friday, July 22, 2016.

 

DATED at the City of Vancouver, in the Province of British Columbia, this       13th       day of July 2016.

 

BY ORDER

Original signed by:

D. M. Morton

Commissioner

 

Attachment


APPENDIX A

to Order G-110-16

Page 1 of 1

 

 

 

 

Sun Peaks Utilities Co., Ltd.

Application for Approval of a Delivery Rate Increase

 

ACTION

DATE (2016)

Sun Peaks Utilities Co., Ltd. provide notice to customers

Friday, July 22

Intervener Registration

Friday, July 29

Commission Information Request No. 1

Wednesday, August 3

Intervener Information Request No. 1

Friday, August 5

Sun Peaks Utilities Co., Ltd. Responses to Commission and Intervener Information Requests

Friday, August 12

 