Re: FortisBC Energy Inc.
Gas Supply Mitigation Incentive Program (GSMIP) for the Period November 1, 2016 to October 31, 2019
Order G-141-16 – GSMIP Term Sheet Compliance Filing
By Order G-141-16, the British Columbia Utilities Commission (Commission) approved the FortisBC Energy Inc. (FEI) Gas Supply Mitigation Incentive Program (GSMIP) extension for a three year term for the period November 1, 2016 to October 31, 2019 (2016-2019 GSMIP), subject to the terms set out in that Order.
In Directive 2 of Order G-141-16, FEI was directed to notify stakeholders when GSMIP reports are filed with the Commission to keep stakeholders informed and revise the 2016-2019 GSMIP Term Sheet accordingly. On September 19, 2016, in compliance with Order G-141-16, FEI filed a revised 2016-2019 GSMIP Term Sheet for Commission acceptance.
The Commission reviewed the filing and considers that the revised 2016-2019 GSMIP Term Sheet meets the terms set out in Directive 2 of Order G-141-16. The Commission accepts the revised 2016-2019 GSMIP Term Sheet, attached as Appendix A to this letter.
Yours truly,
Original signed by
Patrick Wruck for:
Laurel Ross