Orders

Decision Information

Decision Content

ORDER NUMBER

G-63-17

 

IN THE MATTER OF

the Utilities Commission Act, RSBC 1996, Chapter 473

 

and

 

FortisBC Energy Inc.

Application for Approval of Rates for Constructing and Operating a Compressed Natural Gas Fueling Station under the Province’s Greenhouse Gas Reduction (Clean Energy) Regulation for

Nanaimo Cold Storage and Trucking Ltd., the City of Nanaimo and Coldstar Solutions Inc. at

Mid Island Consumer Services Co-operative

 

BEFORE:

K. A. Keilty, Commissioner

 

on May 1, 2017

 

ORDER

WHEREAS:

 

A.      On February 3, 2017, FortisBC Energy Inc. (FEI) applied to the British Columbia Utilities Commission (Commission), pursuant to sections 59 to 61 of the Utilities Commission Act (UCA), for permanent approval of the rate design and rates established in the fueling services agreement between FEI and the Nanaimo Cold Storage and Trucking Ltd. (Nanaimo Cold), effective August 1, 2016 (Application);

B.      On April 11, 2013, the Commission issued Order G-56-13 accepting that the Greenhouse Gas Reduction Regulation (GGRR) established the need for Compressed Natural Gas (CNG) and Liquefied Natural Gas fueling stations that are undertaken by FEI as prescribed undertakings as defined by the GGRR, and that these prescribed undertaking projects are exempt from the Certificate of Public Convenience and Necessity requirements for the term of the GGRR;

C.      On November 27, 2013, the Lieutenant Governor in Council issued Order in Council No. 556 amending the GGRR. The GGRR was further amended by Order in Council No. 297, dated June 3, 2015;

D.      On January 14, 2016, FEI and Nanaimo Cold entered into a fueling services agreement that establishes the terms, conditions and rates for the City of Nanaimo to receive CNG fueling service from the FEI CNG station located at Mid Island Consumer Services Co-operative, in Nanaimo, British Columbia (Mid Island Fueling Station);

E.       On April 22, 2016, FEI applied to the Commission, pursuant to sections 59 to 61 and 89 of UCA, for among other things, interim and permanent approval of the rate design and rates established in the fueling services agreement between FEI and Nanaimo Cold, effective August 1, 2016. FEI also requested that the Commission keep confidential the live financial model in Confidential Appendix D;

F.       On June 29, 2016, Order G-100-16 approved the rate design and rates established in the fueling services agreement between FEI and Nanaimo Cold on an interim basis, effective August 1, 2016. The order also approved FEI’s request to hold confidential the live financial model in Confidential Appendix D and directed FEI to file an application seeking permanent rates, effective on August 1, 2016, upon the determination of the actual capital expenditures for the Mid Island Fueling Station; and

G.     The Commission reviewed the Application and determines permanent rates should be approved.

 

NOW THEREFORE pursuant to sections 59 to 61 of the Utilities Commission Act, the British Columbia Utilities Commission orders as follows:

 

1.       The rate design and rates established in the fueling services agreement between FortisBC Energy Inc. and Nanaimo Cold Storage and Trucking Ltd. are approved on a permanent basis, effective on August 1, 2016.

2.       FortisBC Energy Inc. is to file the fueling services agreement between FortisBC Energy Inc. and the Nanaimo Cold Storage and Trucking Ltd. in tariff supplement form for endorsement by the Commission within 30 days of the date of this order.

 

DATED at the City of Vancouver, in the Province of British Columbia, this          2nd            day of May 2017.

 

BY ORDER

Original signed by:

K. A. Keilty

Commissioner

 

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.