Orders

Decision Information

Decision Content

 

ORDER NUMBER

G-51-18

 

IN THE MATTER OF

the Utilities Commission Act, RSBC 1996, Chapter 473

 

and

 

FortisBC Inc.

Self-Generation Policy Stage II Application

 

BEFORE:

H. G. Harowitz, Panel Chair/Commissioner

M. Kresivo, QC, Commissioner

R. I. Mason, Commissioner

D. M. Morton, Commissioner

 

on March 2, 2018

 

ORDER

WHEREAS:

 

A.      On November 10, 2016, FortisBC Inc. (FBC) filed with the British Columbia Utilities Commission (Commission) its Self-Generation Policy Stage II Application, seeking among other things, approval of the Self-Supply Obligation Guidelines and the Stand-by Billing Demand (Application);

B.      On January 8, 2018, the Commission issued Order G-2-18, amending the Regulatory Timetable to include the issue of Commission Information Request (IR) No. 2 and Intervener IR No. 1 on February 8, followed by FBC responses to IRs on March 8;

C.      On February 27, 2018, FBC submitted a request for extension of deadlines in the Regulatory Timetable, as set out by Order G-2-18; and

D.      The Panel has considered reasons for the request, and finds it appropriate to resume the proceeding in line with the amended Regulatory Timetable set out in this order.

 

NOW THEREFORE British Columbia Utilities Commission orders that the proceeding be revised, according to the amended Regulatory Timetable below.

 

Action

Date (2018)

FBC responses to Commission IR No. 2 and Intervener IRs No. 1

Friday, March 16

Further process

TBD

 

 

DATED at the City of Vancouver, in the Province of British Columbia, this               2nd            day of March 2018.

 