ORDER NUMBER
G-51-18
IN THE MATTER OF
the Utilities Commission Act, RSBC 1996, Chapter 473
and
FortisBC Inc.
Self-Generation Policy Stage II Application
BEFORE:
H. G. Harowitz, Panel Chair/Commissioner
M. Kresivo, QC, Commissioner
R. I. Mason, Commissioner
D. M. Morton, Commissioner
on March 2, 2018
ORDER
WHEREAS:
A. On November 10, 2016, FortisBC Inc. (FBC) filed with the British Columbia Utilities Commission (Commission) its Self-Generation Policy Stage II Application, seeking among other things, approval of the Self-Supply Obligation Guidelines and the Stand-by Billing Demand (Application);
B. On January 8, 2018, the Commission issued Order G-2-18, amending the Regulatory Timetable to include the issue of Commission Information Request (IR) No. 2 and Intervener IR No. 1 on February 8, followed by FBC responses to IRs on March 8;
C. On February 27, 2018, FBC submitted a request for extension of deadlines in the Regulatory Timetable, as set out by Order G-2-18; and
D. The Panel has considered reasons for the request, and finds it appropriate to resume the proceeding in line with the amended Regulatory Timetable set out in this order.
NOW THEREFORE British Columbia Utilities Commission orders that the proceeding be revised, according to the amended Regulatory Timetable below.
Action |
Date (2018) |
FBC responses to Commission IR No. 2 and Intervener IRs No. 1 |
Friday, March 16 |
Further process |
TBD |
DATED at the City of Vancouver, in the Province of British Columbia, this 2nd day of March 2018.
BY ORDER
Original signed by:
H. G. Harowitz
Commissioner