Orders

Decision Information

Decision Content

ORDER NUMBER

G-71-18

 

IN THE MATTER OF

the Utilities Commission Act, RSBC 1996, Chapter 473

 

and

 

Nelson Hydro

2018 Rate Application

 

BEFORE:

A. K. Fung, QC, Panel Chair/Commissioner

 

on April 6, 2018

 

ORDER

WHEREAS:

 

A.      On December 8, 2017, Nelson Hydro filed an application with the British Columbia Utilities Commission (BCUC) for approval of a general rate increase of 2.25 percent, effective April 1, 2018 (Application);

B.      Nelson Hydro is owned and operated by the City of Nelson and is exempt from regulation under the Utilities Commission Act to the extent it is serving customers within its municipal boundaries. Accordingly, while the requested rate increase will be applied uniformly to all ratepayers receiving service both inside and outside the City of Nelson’s municipal boundaries,  BCUC’s review of the Application pertains solely to Nelson Hydro’s non-municipal, or rural, ratepayers;

C.      By Order G-13-18 dated January 17, 2018,  BCUC approved the applied for rate increase of 2.25 percent on an interim and refundable basis, effective April 1, 2018. BCUC also established an initial regulatory timetable, which included intervener and interested party registration and one round of BCUC and intervener information requests (IRs); and

D.      The Panel has reviewed Nelson Hydro’s responses to IR No. 1 and considers that a second round of IRs followed by written argument is warranted.

 

NOW THEREFORE the British Columbia Utilities Commission establishes the remainder of the regulatory timetable, attached as Appendix A to this order.

 

 

DATED at the City of Vancouver, in the Province of British Columbia, this      6th      day of April 2018.

 

BY ORDER

 

Original signed by:

 

A. K. Fung, QC

Commissioner

 

Attachment


Nelson Hydro

2018 Rate Application

 

REGULATORY TIMETABLE

 

 

Action

Date (2018)

BCUC and Intervener Information Request (IR) No. 2

Thursday, April 19

Nelson Hydro response to BCUC and Intervener IR No. 2

Thursday, May 10

Letters of Comment Deadline

Thursday, May 17

Nelson Hydro Written Final Argument

Friday, May 25

Intervener Written Final Argument (if applicable)

Friday, June 1

Nelson Hydro Written Reply Argument (if applicable)

Friday, June 8


 

 

 

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.