April 26, 2018

                                                                                                                                                                                                                               

Sent via email

                                                                                                                                                                                                      Letter L-8-18

 

Ms. Diane Roy

Director, Regulatory Affairs

FortisBC Inc.

16705 Fraser Highway

Surrey, BC   V4N 0E8

electricity.regulatory.affairs@fortisbc.com

 

Re:         FortisBC Inc. – 2018/2019 Annual Electric Contracting Plan

 

Dear Ms. Roy:

On March 23, 2018, FortisBC Inc. (FBC) filed its 2018/2019 Annual Electric Contracting Plan (AECP) for the period from October 1, 2018 to September 30, 2019 (2018/2019 operating year) for acceptance by the British Columbia Utilities Commission (BCUC).

 

The AECP outlines FBC’s plans to meet the peak demand requirements and annual energy requirements for the 2018/2019 operating year and the near future. The major components of the 2018/2019 AECP are:

 

         A Nomination under the Power Purchase Agreement between FBC and BC Hydro for the 2018/2019 operating year equal to 683 GWh, less any firm market contracts that FBC can enter into, pursuant to section 5 of the 2018/2019 AECP; and

         FBC’s proposed plan for entering into firm market contracts for operating years 2018/2019 through 2021/2022, which includes a maximum market purchase of 80 GWh prior to June 30, 2018 for operating year 2018/2019.

 

The BCUC accepts the FBC 2018/2019 AECP and the recommendations contained therein.

 

The information in the FBC 2018/2019 AECP will be treated as confidential, as requested by FBC, as it contains commercially sensitive information. A copy of the non-confidential Executive Summary for the FBC 2018/2019 AECP is available to the public and is attached to this letter.

 

Sincerely,

 

 

 

Patrick Wruck

Commission Secretary

 

AP/dg