ORDER NUMBER
G-143-18
IN THE MATTER OF
the Utilities Commission Act, RSBC 1996, Chapter 473
and
FortisBC Energy Inc.
Annual Review for 2019 Delivery Rates
BEFORE:
R. I. Mason, Panel Chair/Commissioner
D. J. Enns, Commissioner
on July 31, 2018
ORDER
WHEREAS:
A. On September 15, 2014, the British Columbia Utilities Commission (BCUC) issued its Decision and Order G-138-14 for FortisBC Energy Inc. (FEI) approving a Multi-Year Performance Based Ratemaking (PBR) Plan for 2014 through 2019 (PBR Decision). In accordance with the PBR Decision, an annual review process with the BCUC will be undertaken to set delivery rates for each year;
B. On May 27, 2015, the BCUC issued its Decision and Order G-86-15 in the FEI Annual Review for 2015 Delivery Rates application, setting out, among other things, the regulatory timetable template for future annual reviews, which includes:
• Intervener registration;
• One round of BCUC and intervener information requests;
• A workshop which may include BCUC panel participation. The format of the workshop, including who facilitates it, will be determined at each annual review proceeding;
• FEI response to undertakings from the workshop;
• Intervener written final arguments; and
• FEI written reply argument;
C. By letter dated July 26, 2018, FEI proposed a regulatory timetable for its annual review for 2019 delivery rates; and
D. The BCUC has reviewed FEI’s proposal and considers that establishment of a regulatory timetable for the annual review for FEI’s 2019 delivery rates is warranted.
NOW THEREFORE the BCUC orders as follows:
1. The regulatory timetable for the annual review for FEI’s 2019 delivery rates is established, as set out in Appendix A to this order.
2. A workshop to review FEI’s 2018 performance results and the 2019 revenue requirements will be held on Tuesday, October 2, 2018, commencing at 9:00 a.m., at the BCUC Hearing Room on the 12th Floor, 1125 Howe Street, Vancouver, BC.
3. Interveners are to register with the BCUC by completing a Request to Intervene form, available on the BCUC’s website, by the date established in the regulatory timetable attached as Appendix A to this order, and in accordance with the BCUC’s Rules of Practice and Procedure attached to Order G-1-16.
DATED at the City of Vancouver, in the Province of British Columbia, this 31st day of July 2018.
BY ORDER
Original signed by:
R. I. Mason
Commissioner
Attachment
FortisBC Energy Inc.
Annual Review for 2019 Delivery Rates
REGULATORY TIMETABLE
Action |
Date (2018) |
FEI filing of 2019 Annual Review Application on or before |
Friday, August 3 |
Intervener registration |
Friday, August 10 |
Participant Assistance/Cost Award (PACA) Budget |
Wednesday, August 15 |
BCUC and Intervener Information Request (IR) No. 1 |
Monday, August 27 |
FEI responses to BCUC and Intervener IR No. 1 |
Tuesday, September 18 |
Workshop* |
Tuesday, October 2 |
FEI responses to workshop undertakings (if any) |
Thursday, October 11 |
Intervener written final argument |
Thursday, October 25 |
FEI written reply argument |
Thursday, November 1 |
*Workshop Location:
BCUC Hearing Room
12th Floor, 1125 Howe Street
Vancouver, BC
Commencing at 9:00 a.m.