Orders

Decision Information

Decision Content

 

ORDER NUMBER

G-155-18

 

IN THE MATTER OF

the Utilities Commission Act, RSBC 1996, Chapter 473

 

and

 

British Columbia Hydro and Power Authority

Application for Approval to Remove Rate Schedule 1278 from the Electric Tariff

 

BEFORE:

D. A. Cote, Commissioner

 

on August 17, 2018

 

ORDER

WHEREAS:

 

A.      By letter dated May 4, 2018, British Columbia Hydro and Power Authority (BC Hydro) filed an application with the British Columbia Utilities Commission (BCUC) for approval to remove Rate Schedule (RS) 1278 from its Electric Tariff effective the date of the BCUC order approving this change (Application);

B.      BC Hydro requests approval to remove RS 1278 from its Electric Tariff as it is a closed rate and the last customer account on this rate was closed in July 2017; and

C.      The BCUC has reviewed the Application and considers that approval is warranted.

 

NOW THEREFORE the BCUC orders as follows:

 

1.       The removal of RS 1278 from BC Hydro’s Electric Tariff is approved, effective the date of this order.

2.       BC Hydro is directed to file with the BCUC amended tariff sheets within 15 business days of this order.

 

DATED at the City of Vancouver, in the Province of British Columbia, this                17th              day of August 2018.

 

BY ORDER

 

Original signed by

 

D. A. Cote

Commissioner

 

 

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.