Orders

Decision Information

Decision Content

 

ORDER NUMBER

G-181-18

 

IN THE MATTER OF

the Utilities Commission Act, RSBC 1996, Chapter 473

 

and

 

FortisBC Alternative Energy Services Inc.

Stream A Registration of the Mahogany Thermal Energy System

 

BEFORE:

H. G. Harowitz, Panel Chair/Commissioner

B. A. Magnan, Commissioner

R. D. Revel, Commissioner

 

on September 25, 2018

 

ORDER

WHEREAS:

A.      On September 6, 2018, FortisBC Alternative Energy Services Inc. (FAES), filed with the British Columbia Utilities Commission (BCUC) an application to register the Mahogany Stream A Thermal Energy System (Mahogany TES), in accordance with the Thermal Energy Systems (TES) Regulatory Framework Guidelines (TES Guidelines);

B.      On August 28, 2014, the BCUC issued Order G-127-14 approving the TES Guidelines;

C.      Under section 2.1 of the TES Guidelines, a Stream A TES is defined as: An On-Site TES with an Initial Capital Cost above $500,000 but less than $15,000,000 is exempt from sections 44.1, 45 and 59-61 of the Utilities Commission Act (UCA). TES Providers are required to register Stream A TES prior to building or otherwise acquiring the Stream A TES; and

D.      The BCUC has reviewed the application and is satisfied that the Mahogany TES meets the characteristics of a Stream A TES and is suitable for exemption from sections 44.1, 45 and 59-61 of the UCA. 

 


 

NOW THEREFORE pursuant to section 88(3) of the UCA and by the advance approval of the Lieutenant Governor in Council (OIC 400), the BCUC orders as follows:

 

1.       In accordance with the TES Guidelines, the Mahogany TES is exempt from sections 44.1, 45 and 59-61 of the UCA.

 

2.       FAES must file with the BCUC an annual report for the Mahogany TES, in accordance with Stream A annual reporting guidelines as provided in Appendix B of the TES Guidelines.

 

DATED at the City of Vancouver, in the Province of British Columbia,             this 25th         day of September 2018.

 

BY ORDER

 

Original Signed by:

 

H. G. Harowitz

Commissioner

 

 

 