Orders

Decision Information

Decision Content

ORDER NUMBER

G-223-18

 

IN THE MATTER OF

the Utilities Commission Act, RSBC 1996, Chapter 473

 

and

 

British Columbia Hydro and Power Authority

Review of the Regulatory Oversight of Capital Expenditures and Projects

 

BEFORE:

K. A. Keilty, Panel Chair/Commissioner

W. M. Everett, Q.C., Commissioner

R. I. Mason, Commissioner

 

 

on November 27, 2018

 

 

ORDER

WHEREAS:

 

A.      On May 3, 2016, the British Columbia Utilities Commission (BCUC) issued Order G-58-16, establishing a proceeding to review the regulatory oversight of British Columbia Hydro and Power Authority’s (BC Hydro) capital expenditures and projects (Review);

B.      By Order G-193-18 dated October 11, 2018, the BCUC set out a regulatory timetable which included the filing of evidence by the Commercial Energy Consumers Association of British Columbia (CEC), and the filing of rebuttal evidence by BC Hydro;

C.      On November 5, 2018, CEC filed evidence with the BCUC;

D.      By letter dated November 23, 2018, BC Hydro requested an extension to the filing deadline for its rebuttal evidence. BC Hydro submits that it requires additional time to assess and respond to CEC’s evidence due to resources needed for the preparation of its next Revenue Requirements Application, the CEC evidence touching on all of BC Hydro’s capital business groups, and the evidence including a new proposal not previously considered in this or any other proceeding. BC Hydro also submits that it would be helpful if a report with respect to the Government Review of BC Hydro, expected to be released at the beginning of the year, is available to inform BC Hydro’s rebuttal evidence; and

E.       The BCUC has reviewed the request of BC Hydro and considers an amendment to the regulatory timetable for the Review established by Order G-193-18 is warranted.

 

 

NOW THEREFORE the BCUC orders as that the regulatory timetable for the Review established by Order
G-193-18 is amended and attached as Appendix A to this order.

 

DATED at the City of Vancouver, in the Province of British Columbia, this     27th   day of November 2018.

 

BY ORDER

 

Original signed by:

 

K. A. Keilty

Commissioner

 

 

Attachment

 

 


British Columbia Hydro and Power Authority

Review of the Regulatory Oversight of Capital Expenditures and Projects

 

REGULATORY TIMETABLE

 

 

Action

Date

CEC Responses to IRs on CEC Evidence

Monday, December 3, 2018

BC Hydro to File Rebuttal Evidence

Friday, January 25, 2019

BCUC and Intervener IRs on BC Hydro Revised Proposal and Rebuttal Evidence

Thursday, February 28, 2019

BC Hydro Responses to IRs on BC Hydro Revised Proposal and Rebuttal Evidence

Thursday, March 21, 2019

BC Hydro Final Argument

Thursday, April 4, 2019

Intervener Final Argument

Thursday, April 18, 2019

BC Hydro Reply Argument

Thursday, May 2, 2019

 

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.