ORDER NUMBER
G-253-19
IN THE MATTER OF
the Utilities Commission Act, RSBC 1996, Chapter 473
and
CB Powerline Ltd.
Application for an exemption pursuant to section 88(3) of the Utilities Commission Act
BEFORE:
T. A. Loski, Panel Chair
C. M. Brewer, Commissioner
W. M. Everett, QC, Commissioner
on October 23, 2019
ORDER
WHEREAS:
A. On June 13, 2019, CB Powerline Ltd. (CBP) filed an application with the British Columbia Utilities Commission (BCUC) for an exemption from all of Part 3 of the Utilities Commission Act (UCA), pursuant to section 88(3) of the UCA, with respect to the proposed provision of electricity to the community of Cosens Bay, Regional District of North Okanagan, British Columbia (Application);
B. CBP was founded with the purpose of providing electricity supply to the community of Cosens Bay;
C. CBP intends to apply to the British Columbia Hydro and Power Authority (BC Hydro) for a Primary Service Connection to BC Hydro’s 25 kV distribution system. CBP would in turn construct and operate an electricity distribution system to provide year-round electricity supply to the Cosens Bay community;
D. On July 8, 2019, by Order G-151-19, the BCUC established a written hearing process and a regulatory timetable to review the Application. The regulatory timetable included intervener registration, one round of information requests and submissions on further process;
E. BC Hydro and FortisBC Inc. (FBC) registered as interveners;
F. On October 17, 2019, CBP and FBC made submissions on further process. CBP recommended proceeding to final arguments and FBC made no comment on further process; and
G. The BCUC has reviewed the submissions and considers that a further regulatory timetable is warranted.
NOW THEREFORE the BCUC orders that a further regulatory timetable for the review of the Application is established, as set out in Appendix A to this order.
DATED at the City of Vancouver, in the Province of British Columbia, this 23rd day of October 2019.
BY ORDER
Original signed by:
T. A. Loski
Commissioner
Attachment
Application for an exemption pursuant to section 88(3) of the Utilities Commission Act
REGULATORY TIMETABLE
ACTION |
Date (2019) |
BCUC Information Request (IR) No. 1 to BC Hydro |
Thursday, November 21 |
BC Hydro response to BCUC IR No. 1 |
Thursday, December 5 |
BCUC and Intervener IR No. 2 to CBP |
Thursday, December 12 |
ACTION |
DATE (2020) |
CBP response to BCUC and Intervener IR No. 2 |
Thursday, January 9 |
CBP Written Final Argument |
Thursday, January 23 |
Intervener Written Final Argument |
Thursday, January 30 |
CBP Reply Argument |
Thursday, February 6 |