ORDER NUMBER

G-269-19

 

IN THE MATTER OF

the Utilities Commission Act, RSBC 1996, Chapter 473

 

and

 

British Columbia Utilities Commission

Indigenous Utilities Regulation Inquiry

 

BEFORE:

D. M. Morton, Panel Chair

C. M. Brewer, Commissioner

A. K. Fung, QC, Commissioner

E. B. Lockhart, Commissioner

 

on November 1, 2019

 

ORDER

WHEREAS:

 

A.      On March 11, 2019, by Order in Council (OIC) No. 108, made pursuant to section 5(1) of the Utilities Commission Act (UCA), the Lieutenant Governor in Council directed the British Columbia Utilities Commission (BCUC) to advise the Lieutenant Governor in Council respecting the regulation of Indigenous utilities in accordance with the terms of reference set out in section 3 of OIC No. 108 (Indigenous Utilities Regulation Inquiry);

B.      Section 3 of OIC No. 108 also provides that the BCUC must submit reports to the minister responsible for the Hydro and Power Authority Act, as follows:

1.       An interim report describing the BCUC's progress to date and the BCUC’s preliminary findings must be submitted no later than December 31, 2019; and

2.       A final report describing the results of consultations undertaken by the BCUC and the BCUC's findings and recommendations must be submitted no later than January 31, 2020;

C.      By Order G-62-19 dated March 19, 2019, the BCUC established the Indigenous Utilities Regulation Inquiry;  

D.      By Order G-240-19 dated October 7, 2019, the BCUC issued a regulatory timetable for the Indigenous Utilities Regulation Inquiry;

E.        By OIC No. 559 dated October 31, 2019, the Lieutenant Governor in Council amended section 3 of OIC No. 108 for the Indigenous Utilities Regulation Inquiry by striking out “January 31, 2020” and substituting “April 30, 2020”; and

F.       As a result, the BCUC considers that an amendment to the regulatory timetable for the Indigenous Utilities Regulation Inquiry is warranted.

 

NOW THEREFORE the BCUC amends the regulatory timetable established by Order G-214-19. The amended regulatory timetable is attached as Appendix A to this order.

 

 

DATED at the City of Vancouver, in the Province of British Columbia, this             1st              day of November 2019.

 

BY ORDER

 

Original signed by:

 

D. M. Morton

Commissioner

 

 

Attachment

 

 


British Columbia Utilities Commission

Indigenous Utilities Regulation Inquiry

 

REGULATORY TIMETABLE

 

Action

Date

Draft report issued for comment

Friday, November 1, 2019

Workshop – Prince George, Coast Inn of the North

Monday, November 18, 2019

Workshop – Kelowna, Sandman Hotel

Thursday, November 21, 2019

Workshop – Vancouver, Allwest Reporting
(12th Floor, 1125 Howe St)

Wednesday, November 27, 2019

Workshop – Nanaimo, Coast Bastion Hotel

Thursday, November 28, 2019

Workshop– Victoria, Comfort Inn & Suites

Friday, November 29, 2019

Workshop – Smithers, Hudson Bay Lodge

Monday, December 9, 2019

Interim Report issued to the minister responsible for

the Hydro and Power Authority Act

Tuesday, December 31, 2019

Written comments on the draft report

Monday, March 2, 2020

Written reply to comments from other participants on draft report

Tuesday, March 31, 2020

Final Report issued to minister responsible for the

Hydro and Power Authority Act

Thursday, April 30, 2020

 

 

 

 

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.