Orders

Decision Information

Decision Content

ORDER NUMBER

G-37-20

 

IN THE MATTER OF

the Utilities Commission Act, RSBC 1996, Chapter 473

 

and

 

Boralex Ocean Falls Limited Partnership

Application for Approval of Rates and Terms and Conditions for

Service to British Columbia Hydro and Power Authority

BEFORE:

B. A. Magnan, Panel Chair

W. M. Everett, QC, Commissioner

R. I. Mason, Commissioner

 

on Date March 2, 2020

 

ORDER

WHEREAS:

 

A.      On September 30, 2019, Boralex Ocean Falls Limited Partnership (Boralex) applied to the British Columbia Utilities Commission (BCUC) for approval of interim and permanent rates for service to British Columbia Hydro and Power Authority (BC Hydro) for the period of July 1, 2019 to December 31, 2022, terms and conditions for service to BC Hydro and the First Nations relationship building deferral account (Application). The Application is made pursuant to Orders G-143-19 and G-202-19;

B.      By Order G-3-20, dated January 3, 2020, the BCUC established an updated regulatory timetable, which included BCUC and intervener Information Requests (IRs) and further process to be determined;

C.      On February 3, 2020, the BCUC and interveners filed IRs with Boralex. On February 24, 2020, Boralex filed IR responses, and indicated that it would file updates to certain information with the BCUC by March 9, 2020; and

D.      The BCUC finds that establishing an updated regulatory timetable is warranted.

 

NOW THEREFORE the BCUC establishes an updated regulatory timetable for the review of the Application, as set out in Appendix A to this order.

 

 

 

 


 

DATED at the City of Vancouver, in the Province of British Columbia, this                2nd               day of March 2020.

 

BY ORDER

 

Original Signed By:

 

B. A. Magnan

Commissioner

 

 

Attachment

 

 


Boralex Ocean Falls Limited Partnership

Application for Approval of Rates and Terms and Conditions for

Service to British Columbia Hydro and Power Authority

 

REGULATORY TIMETABLE

 

 

Action

Date (2020)

Boralex to file information updates

Monday, March 9

BCUC and Intervener Information Request (IR) No. 2 to Boralex

Monday, March 23

Boralex responses to BCUC and Intervener IR No. 2

Wednesday, April 15

Further process

To be determined

 