ORDER NUMBER
G-205-20
IN THE MATTER OF
the Utilities Commission Act, RSBC 1996, Chapter 473
and
British Columbia Hydro and Power Authority
Long-Term Resource Plan Filing Date
BEFORE:
D. M. Morton, Panel Chair
C. M. Brewer, Commissioner
R. I. Mason, Commissioner
on July 30, 2020
ORDER
WHEREAS:
A. Pursuant to section 44.1 (2) of the Utilities Commission Act (UCA), subject to subsection (2.1), a public utility must file a long-term resource plan with the British Columbia Utilities Commission (BCUC) in the form and at the times the BCUC requires;
B. Pursuant to section 44.1, subsection (2.1) of the UCA, British
Columbia Hydro and Power Authority
(BC Hydro) need not file a long-term resource plan before February 28, 2021;
C. Although BC Hydro is currently developing its long-term resource plan, the last time the BCUC reviewed BC Hydro’s long-term resource plan was in 2010. The lack of a more recent plan impedes the BCUC’s ability to efficiently discharge its regulatory responsibilities in relation to BC Hydro; and
D. The BCUC considers that establishing a public hearing for the review of the long-term resource plan filing date is warranted.
NOW THEREFORE, pursuant to section 44.1(2) of the UCA, the BCUC orders as follows:
1. A written hearing process is established for the review of the long-term resource plan filing date in accordance with the regulatory timetable as set out in Appendix A to this order.
2. By Thursday, August 6, 2020, BC Hydro is to:
a. publish this order and the Appendix A on its website;
b. provide a copy of this order and the Appendix A to the participants in the BC Hydro F2020 to F2021 Revenue Requirements Application proceeding; and
c. communicate this order and Appendix A to all the parties that BC Hydro is currently consulting with or that have expressed an interest in being consulted on the BC Hydro long-term resource plan.
3. By Thursday, August 20, 2020, BC Hydro is to submit to the BCUC, with rationale:
a. the date by which BC Hydro will file its next long-term resource plan; and
b. a proposal for an interim filing of BC Hydro’s current planning context that would, in the absence of a recently filed long-term resource plan, aid in the review of BC Hydro applications filed prior to the BCUC review of the next BC Hydro long-term resource plan.
DATED at the City of Vancouver, in the Province of British Columbia, this 30th day of July 2020.
BY ORDER
Original signed by:
D. M. Morton
Commissioner
Attachment
British Columbia Hydro and Power Authority
Long-Term Resource Plan Filing Date
REGULATORY TIMETABLE
Action |
Date (2020) |
BC Hydro to publish this order and the Appendix A |
Thursday, August 6 |
BC Hydro long-term resource plan and interim filing submissions |
Thursday, August 20 |
Intervener registration |
Thursday, August 20 |
Intervener submissions |
Thursday, September 3 |
BC Hydro reply to intervener submissions |
Thursday, September 17 |
Further process |
To be determined |