September 17, 2020                                                                                                                                                                                       

 

Sent via email                                                                                                                                                                        Letter L-58-20

 

Ms. Diane Roy

Vice President, Regulatory Services

FortisBC Energy Inc.

16705 Fraser Highway

Surrey, BC V4N 0E8

gas.regulatory.affairs@fortisbc.com

 

Re:         FortisBC Energy Inc. – Receipt Point Fuel Percentages Effective November 1, 2020

 

Dear Ms. Roy:

 

By this letter, the BCUC approves FortisBC Energy Inc.’s application to maintain the Receipt Point Fuel Percentages for Station 2 at 4.8 percent and for AECO at 1.3 percent, effective November 1, 2020.

FortisBC Energy Inc. is to provide a copy of this letter to all commodity providers participating in Commodity

Unbundling Service under the Customer Choice Program.

 

 

Sincerely,

 

Original signed by Ian Jarvis for:

 

Marija Tresoglavic                                                                                                       

Acting Commission Secretary

 