ORDER NUMBER

G-167-21

 

IN THE MATTER OF

the Utilities Commission Act, RSBC 1996, Chapter 473

 

and

 

Vancouver Airport Fuel Facilities Corporation

Complaint Regarding Jet Fuel Line Abandonment of Service

 

BEFORE:

D. M. Morton, Panel Chair

 

on May 28, 2021

 

ORDER

WHEREAS:

 

A.      By letter dated April 30, 2021, PKM Canada (Jet Fuel) Inc. (PKMJF) informed the British Columbia Utilities Commission (BCUC) that the company’s approximately 41 kilometer long pipeline used to transport aviation turbine fuel (jet fuel) from the Westridge Marine Terminal in Burnaby to the Vancouver International Airport (the Jet Fuel Line, or JFL) had been shutdown effective immediately;

 

B.      By letter dated May 14, 2021, PKMJF informed the BCUC of its intention to permanently discontinue service on the JFL;

 

C.       By letter dated May 14, 2021, the Vancouver Airport Fuel Facilities Corporation (VAFFC) filed a complaint with the BCUC regarding the current abandonment of service of the JFL and PKMJF’s intention to permanently abandon service;

 

D.      By letter dated May 17, 2021, the BCUC requested that PKMJF host recurring Monday/Wednesday/Friday conference calls open to shippers, BCUC staff, and other interested parties to provide updates on the JFL and to answer questions;

 

E.       By Order G-154-21, dated May 20, 2021, PKMJF was directed to continue hosting recurring conference calls with the BCUC, BC Oil and Gas Commission (BCOGC), shippers of JFL and YVR representatives until such time as the BCUC directs otherwise;

 

F.       On May 27, 2021, pursuant to Order G-154-21, PKMJF filed a return to service plan for the JFL (Plan) with the BCUC. In the Plan, PKMJF states that it is unable to restore service on the JFL by June 19, 2021, as required; and

 

G.      The BCUC has reviewed the Plan and considers that further regulatory process is warranted.

 

 

NOW THEREFORE the BCUC orders as follows:

 

1.       A regulatory timetable for the proceeding is established as set out in Appendix A to this order.

2.       PKMJF is directed to publish this order and the regulatory timetable on the Pembina Pipeline Corporation website and to provide a copy of same to those attending the recurring PKMJF conference calls, including the BCOGC, shippers of JFL and YVR representatives, by Monday, May 31, 2021.

 

 

DATED at the City of Vancouver, in the Province of British Columbia, this                 28th              day of May 2021.

 

BY ORDER

 

Original signed by:

 

D. M. Morton

Commissioner


Vancouver Airport Fuel Facilities Corporation

Complaint Regarding Jet Fuel Line Abandonment of Service

 

REGULATORY TIMETABLE

 

 

 

Action

Date (2021)

PKMJF to Provide Notice of the Proceeding

Monday, May 31

Intervener Registration

Friday, June 4

BCUC and Intervener Information Requests (IR) No. 1

Friday, June 4

Letters of Comment

Friday, June 4

PKMJF Responses to BCUC and Intervener IR No. 1 and to Letters of Comment

12:00 p.m., Friday, June 11

Further Process

To be determined

 

                                                                                                                                                                                                               