Orders

Decision Information

Decision Content

 

ORDER NUMBER

R-23-21

 

IN THE MATTER OF

the Utilities Commission Act, RSBC 1996, Chapter 473

 

and

 

British Columbia Hydro and Power Authority

Application for Acceptance of a Mitigation Plan required for

Compliance with Mandatory Reliability Standard:

FAC-002-1 Requirement 1 – Violation ID:  BCUC2021000754

 

BEFORE:

W. M. Everett, QC, Commissioner

 

on October 8, 2021

 

ORDER

WHEREAS:

 

A.      On August 5, 2021, the Western Electricity Coordinating Council (WECC), acting as the Administrator for the British Columbia Mandatory Reliability Standards Program (BC MRS Program), issued a Recommendation of Mitigation Plan (MP) Acceptance (Recommendation) to bring British Columbia Hydro and Power Authority (BC Hydro) into compliance with the reliability standard identified above;

B.      Section 125.2 of the Utilities Commission Act (UCA) assigns exclusive jurisdiction to the British Columbia Utilities Commission (BCUC) to determine whether a “reliability standard,” as defined in the UCA, is in the public interest and should be adopted in British Columbia;

C.      By Order G-123-09, the BCUC appointed WECC as its Administrator for registration and monitoring compliance pursuant to section 8 of the UCA. WECC’s role as Administrator for the BC MRS Program is pursuant to the Administration Agreement between WECC and the BCUC signed on October 8, 2009, and renewed on July 5, 2019;

D.      Order G-123-09 also approved the Compliance Monitoring Program (CMP) for monitoring and enforcement of adopted reliability standards and most recent revisions to the CMP were approved by Order R-40-17, dated September 1, 2017;

E.       Pursuant to section 5.1.1 of the CMP, an entity subject to approved Mandatory Reliability Standards found in Confirmed Violation of a reliability standard must prepare an MP to correct the Confirmed Violation or prepare a description of how the Confirmed Violation has been mitigated. Pursuant to section 5.3.2 of the CMP, an MP with respect to a Confirmed Violation must be submitted to the Administrator within ten days following confirmation by the BCUC;

F.       An MP with respect to a Possible Violation or an Alleged Violation may be submitted at any time and the BCUC encourages entities to mitigate all perceived instances of noncompliance upon detection;

G.      On August 4, 2021, BC Hydro submitted the MP to address the self-reported Possible Violation FAC-002-1 R1 with the proposed completion date of December 20, 2021, as shown below; and

Reliability Standard

BCUC Violation ID

Date MP Submitted to WECC

Proposed Completion Date

FAC-002-1 R1

BCUC2021000754

August 4, 2021

December 20, 2021

 

H.      The BCUC reviewed WECC’s Recommendation and considers that acceptance of the MP for FAC-002-1 R1 is warranted.

 

NOW THEREFORE pursuant to section 125.2(10) of the UCA and in accordance with the CMP, the BCUC accepts the MP with the proposed completion date as identified in recital G above.

 

 

DATED at the City of Vancouver, in the Province of British Columbia, this                8th              day of October 2021.

 

BY ORDER

 

Original signed by:

 

W. M. Everett, QC

Commissioner

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.