WHEREAS:

 

A.      On November 16, 2020, FortisBC Energy Inc. (FEI) submitted an application to the British Columbia Utilities Commission (BCUC) for, among other things, a Certificate of Public Convenience and Necessity pursuant to sections 45 and 46 of the Utilities Commission Act (UCA) for the Okanagan Capacity Upgrade Project (Application);

B.      By Order G-262-21 dated September 7, 2021, the BCUC established a regulatory timetable, which included an oral hearing regarding the oral evidence of Penticton Indian Band (PIB) on November 23, 2021 (Oral Hearing);

C.      By letter dated November 19, 2021, FEI requests that the Oral Hearing and subsequent steps in the proceeding be postponed in order to facilitate further discussions between FEI and PIB. FEI proposes that the Oral Hearing be rescheduled to a date in March 2022, and that the BCUC canvas the availability of participating parties. FEI submits the regulatory timetable should be adjusted accordingly to follow a rescheduled Oral Hearing date;

D.      By letter dated November 19, 2021, PIB agrees with FEI that the regulatory timelines for this proceeding should be suspended and rescheduled for no earlier than March 2021; and

E.       The BCUC determines that establishing an amended regulatory timetable is warranted.

 


 

NOW THEREFORE the BCUC establishes an amended regulatory timetable, as outlined in Appendix A to this order.

 

 

 

DATED at the City of Vancouver, in the Province of British Columbia, this              19th         day of November 2021.

 

BY ORDER

 

Original signed by:

 

R. I. Mason

Commissioner

 

 

Attachment

 

 


FortisBC Energy Inc.

Application for a Certificate of Public Convenience and Necessity

for the Okanagan Capacity Upgrade Project

 

REGULATORY TIMETABLE

 

 

Action

Date (2021)

Intervener submissions on availability for rescheduled Oral Hearing

Monday, November 29

FEI reply submissions on availability for rescheduled Oral Hearing

Monday, December 13

Further process

To be determined

 