ORDER NUMBER

G-353-21

 

IN THE MATTER OF

the Utilities Commission Act, RSBC 1996, Chapter 473

 

and

 

British Columbia Hydro and Power Authority

Application for a Certificate of Public Convenience and Necessity

for the Mainwaring Substation Upgrade Project

 

BEFORE:

A. K. Fung, QC, Panel Chair

E. B. Lockhart, Commissioner

A. Pape-Salmon, Commissioner

 

on December 2, 2021

 

ORDER

WHEREAS:

 

A.      On November 5, 2021, British Columbia Hydro and Power Authority (BC Hydro) filed an application with the British Columbia Utilities Commission (BCUC) pursuant to section 45 and 46 of the Utilities Commission Act (UCA) seeking a Certificate of Public Convenience and Necessity (CPCN) for the Mainwaring substation upgrade project (Application);

B.      In the Application, BC Hydro proposes to replace two power transformers, a feeder section and associated equipment at the Mainwaring distribution substation, which is located in South Vancouver (Project);

C.      BC Hydro states that the expected cost of the Project is $114.4 million;

D.      By Order G-347-21, dated November 26, 2021, the BCUC established a regulatory timetable for the review of the Application, which included public notification, filing of confirmation of compliance with public notification directives, two rounds of BCUC and Intervener information requests, a deadline to submit letters of comments and further process to be determined; and

E.       The BCUC determines that an amendment to the regulatory timetable regarding confirmation of notice is warranted.

 


 

NOW THEREFORE the BCUC orders the regulatory timetable established by Order G-347-21 is amended as set out in Appendix A to this order.

 

 

DATED at the City of Vancouver, in the Province of British Columbia, this             2nd            day of December 2021.

 

BY ORDER

 

Original signed by:

 

A. K. Fung, QC

Commissioner

 

 

Attachment

 

 

 


British Columbia Hydro and Power Authority

Application for a Certificate of Public Convenience and Necessity

for the Mainwaring Substation Upgrade Project

 

REGULATORY TIMETABLE

 

 

Action

Date (2021)

BC Hydro to publish notice of the Application

Thursday, December 9

Action

Date (2022)

Intervener registration deadline

Friday, January 7

BC Hydro to provide confirmation of compliance with public notification directives

Wednesday, January 12

BCUC Information Request (IR) No. 1 to BC Hydro

Thursday, January 13

Intervener IR No. 1 to BC Hydro

Thursday, January 20

BC Hydro responses to BCUC and Intervener IRs No. 1

Thursday, February 17

BCUC and Intervener IR No. 2 to BC Hydro

Thursday, March 17

BC Hydro responses to BCUC and Intervener IRs No. 2

Thursday, April 14

Deadline to submit letters of comment

Tuesday, April 26

Further process

To be determined

 

 

 