Orders

Decision Information

Decision Content

 

ORDER NUMBER

G-358-21

 

IN THE MATTER OF

the Utilities Commission Act, RSBC 1996, Chapter 473

 

and

 

Creative Energy Vancouver Platforms Inc.

Application for a Certificate of Public Convenience and Necessity for the

Core Steam System Decarbonization Project

 

BEFORE:

A. K. Fung, QC, Panel Chair

C. M. Brewer, Commissioner

A. C. Dennier, Commissioner

E. B. Lockhart, Commissioner

 

on December 6, 2021

 

ORDER

WHEREAS:

 

A.      On June 30, 2021, Creative Energy Vancouver Platforms Inc. (Creative Energy) submitted an application to the British Columbia Utilities Commission (BCUC) for a Certificate of Public Convenience and Necessity (CPCN) for the Core Steam System Decarbonization Project (Project) pursuant to sections 45 and 46 of the Utilities Commission Act (UCA) (Application);

B.      The Project consists of the construction and operation of an electric steam boiler plant, an electric substation and related equipment;

C.      Creative Energy also requests approval, pursuant to section 44.2 of the UCA, of the following anticipated expenditures:

1.       $15.775 million for an electric transmission line constructed, owned and operated by the British Columbia Hydro and Power Authority (BC Hydro) from the Murrin substation to the existing Core Steam Plant; and

2.       $1.25 million for a BC Hydro Facilities Study of the transmission line to connect the electric steam plant and substation to the BC Hydro network.

D.      On September 2, 2021, by Order G-258-21, the BCUC established a regulatory timetable for the review of the Application, which included dates for intervener registration, BCUC and intervener information requests (IRs) No. 1 and Creative Energy responses to IRs;

E.       On November 19, 2021, Creative Energy filed its responses to BCUC and intervener IRs;

F.       On December 3, 2021, the BCUC requested further information from Creative Energy regarding the Project and the final adjustments to the Beatty Plant configuration; and

G.      The BCUC has reviewed the IR responses and determines that a further regulatory timetable is warranted.

 

NOW THEREFORE the BCUC orders that a further regulatory timetable for the review of the Application is established, as set out in Appendix A to this order.

 

DATED at the City of Vancouver, in the Province of British Columbia, this               6th                day of December 2021.

 

BY ORDER

 

Original signed by:

 

A. K. Fung, QC

Commissioner

 

Attachment


 

 


Creative Energy Vancouver Platforms Inc.

Application for a Certificate of Public Convenience and Necessity for the Core Steam System Decarbonization Project

 

REGULATORY TIMETABLE

 

 

Action

Date (2022)

BCUC and intervener information requests (IRs) No. 2 to Creative Energy

Friday, January 14

Creative Energy responses to BCUC and Intervener IRs No. 2

Friday, February 4

Submissions on further process

Monday, February 10

 

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.