ORDER NUMBER
G-369-21
IN THE MATTER OF
the Utilities Commission Act, RSBC 1996, Chapter 473
and
British Columbia Hydro and Power Authority (BC Hydro)
Open Access Transmission Tariff (OATT)
Attachment C Amendments Application –
Methodology to Assess Available Transfer Capability
BEFORE:
D. M. Morton, Panel Chair
A. K. Fung, QC, Commissioner
C. M. Brewer, Commissioner
on December 13, 2021
ORDER
WHEREAS:
A. On September 9, 2021, British Columbia Hydro and Power Authority (BC Hydro) filed with the British Columbia Utilities Commission (BCUC) an application seeking approval to Amend Attachment C of the Open Access Transmission Tariff (OATT) pursuant to sections 58 to 61 of the Utilities Commission Act (UCA) (Application);
B. In the Application, BC Hydro seeks approval of the following amendments to Attachment C of the OATT:
1. To delete one sentence in section 4.5.1 of Attachment C to enable BC Hydro to address its amended practice to allow firm counterflow schedules to create firm available transmission capability (ATC) for sale under BC Hydro’s OATT if certain conditions are met; and
2. To address additional housekeeping items in Attachment C;
C. By Order G-284-21, dated September 28, 2021, the BCUC established a public hearing process with a Regulatory Timetable for the review of the Application, which included notice of the Application, intervener registration, and BCUC and Intervener Information Requests (IRs);
D. On October 8, 2021, one of the Interveners, the Commercial Energy Consumers Association of British Columbia (the CEC), submitted a request to extend the Intervener Registration deadline due to difficulties experienced in accessing electronic documents on the BCUC website;
E. By Order G-294-21, date October 13, 2021, the BCUC amended the Regulatory Timetable to align with the Intervener extension request;
F. On November 5, 2021, BC Hydro submitted a request to extend the BC Hydro Responses to BCUC and Intervener IR No.1 to provide more time to allow BC Hydro to prepare responses;
G. By Order G-331-21, dated November 10, 2021, the BCUC amended the Regulatory Timetable to align with BC Hydro’s IR No.1 responses extension request;
H. On November 22, 2021, BC Hydro submitted its responses to BCUC and Intervener IR No.1, which included both public and confidential responses;
I. The BCUC has reviewed BC Hydro’s IR No. 1 responses and determines submissions on further process are warranted.
NOW THEREFORE the BCUC orders that the Regulatory Timetable is amended as set out in Appendix A to this order.
DATED at the City of Vancouver, in the Province of British Columbia, this 13th day of December 2021.
BY ORDER
Original signed by:
D. M. Morton
Commissioner
Attachment
British Columbia Hydro and Power Authority (BC Hydro)
Open Access Transmission Tariff (OATT)
Attachment C Amendments Application –
Methodology to Assess Available Transfer Capability
REGULATORY TIMETABLE
Action |
Date (2021) |
Interveners submissions on further process |
Thursday, December 16 |
BC Hydro reply submissions on further process |
Tuesday, December 21 |
Further Process |
To Be Determined |