ORDER NUMBER

G-392-21

 

IN THE MATTER OF

the Utilities Commission Act, RSBC 1996, Chapter 473

 

and

 

FortisBC Energy Inc.

Extension Request Related to Filing Additional Detailed Operating Terms with the City of Coquitlam

 

BEFORE:

B. A. Magnan, Commissioner

 

on December 23, 2021

 

ORDER

WHEREAS:

 

A.      On December 13, 2021, FortisBC Energy Inc. (FEI) filed a request with the British Columbia Utilities Commission (BCUC) for a further extension to or on before March 31, 2022 to file the additional detailed operating terms that apply to requests made by the City of Coquitlam (City). FEI stated it required additional time to continue negotiations with the City to reach an agreement on some or all of the additional detailed operating terms before filing them with the BCUC (altogether, Extension Request);

B.      On May 16, 2019, pursuant to section 99 of the Utilities Commission Act (UCA), the City filed with the BCUC an application for Reconsideration and Variance of Order G‐80‐19 (Reconsideration Application). In its Reconsideration Application, the City requests that the BCUC reconsider and vary Order G‐80‐19 on the grounds that the BCUC erred in law;

C.      By Order G-114-21, the BCUC ordered that, pursuant to sections 32 and 99 of the UCA, Directive 2 of Order G-80-19 is varied to read that “upon request by the City that FEI remove a portion of the abandoned NPS 20 Pipeline to accommodate a reasonable municipal purpose”;

D.      By Order G-114-21 and accompanying Decision, the Panel requested FEI to file with the BCUC, within 90 days of the date of the Order, additional detailed operating terms with the City;

E.       On July 16, 2021, BCUC staff approved an extension to file the operating agreement to October 15, 2021, for efficiency purposes; and

F.       By Order G-306-21, the BCUC approved a further extension to or on before December 15, 2021; and

G.      The BCUC has reviewed the Extension Request and considers that an extension to the filing of the operating terms is warranted.

 

 

NOW THEREFORE pursuant to section 99 of the UCA, the BCUC orders as follows:

 

The directive contained in section 6.1 of the Decision accompanying Order G-114-21 is varied as follows:

1.       FEI’s request for an extension to the filing deadline of the additional detailed operating terms that apply to requests made by the City to FEI to remove any portion of the abandoned NPS 20 Pipeline, to March 31, 2022 is approved.

 

2.       FEI must submit the additional detailed operating terms that apply to requests made by the City to FEI to remove any portion of the abandoned NPS 20 Pipeline as specified in the Decision accompanying Order G-114-21.

 

 

DATED at the City of Vancouver, in the Province of British Columbia, this            23rd           day of December 2021.

 

BY ORDER

 

Original signed by:

 

B. A. Magnan

Commissioner