ORDER NUMBER
G-317-22
IN THE MATTER OF
the Utilities Commission Act, RSBC 1996, Chapter 473
and
APT Utility Corp.
Status as a Public Utility
BEFORE:
B. A. Magnan, Panel Chair
E. B. Lockhart, Commissioner
A. Pape-Salmon, Commissioner
November 4, 2022
ORDER
WHEREAS:
B. On January 21, 2022, by Order G-16-22, the BCUC suspended the Complaint pending the outcome of a proceeding to determine if APT is a public utility;
C. On August 16, 2022, by Order G-228-22, the BCUC established a regulatory timetable to conduct the review of APT’s status as a public utility with public notice, BCUC Information Request (IR) No. 1 to APT, a letter of comment period, with further process to be determined;
D. On August 25, 2022, by Order G-244-22, the BCUC issued an amended regulatory timetable which granted APT’s request to revise the public notice and to extend the deadline to file BCUC IR No. 1 responses;
E. On September 15, 2022, APT’s response to BCUC IR No. 1 was filed with the BCUC;
F. On September 22, 2022, the British Columbia Old Age Pensioners’ Organization et al (BCOAPO) requested an amendment to the regulatory process to allow for further process to include intervener registration, intervener IR’s, IR responses and final and reply submissions. In the alterative, BCOAPO requested an extension to the deadline for letters of comment;
G. On October 3, 2022, by Order G-273-22, the BCUC issued an amended regulatory timetable to allow for a further round of BCUC IR, an extension to the letter of comment period, with further process to be determined;
H. On October 27, 2022, APT requested a one week extension to the deadline to respond to letters of comment; and
I. The BCUC has reviewed APT’s request and determines that an amendment to the regulatory timetable is warranted.
NOW THEREFORE the BCUC orders that the regulatory timetable established by Order G-273-22 is amended as set out in Appendix A to this order.
DATED at the City of Vancouver, in the Province of British Columbia, this 4th day of November 2022.
BY ORDER
Original signed by:
B. A. Magnan
Commissioner
Attachment
APT Utility Corp
Status as a Public Utility
REGULATORY TIMETABLE
Action |
Date (2022) |
APT response to Letters of Comment |
Thursday, November 10 |
Further process |
To be determined |