ORDER NUMBER
G-321-22
IN THE MATTER OF
the Utilities Commission Act, RSBC 1996, Chapter 473
and
1358037 B.C. Ltd.
Application for Exemption Under
Section 88(3) of the Utilities Commission Act
BEFORE:
C. M. Brewer, Panel Chair
E. B. Lockhart, Commissioner
B. A. Magnan, Commissioner
on November 7, 2022
ORDER
WHEREAS:
A. On September 20, 2022, pursuant to section 88(3) of the Utilities Commission Act (UCA), 1358037 B.C. Ltd. (135BC) applied to the British Columbia Utilities Commission (BCUC) seeking approval for exemption from section 71 and Part 3 of the UCA, excluding sections 25, 38, 42 and 43, with respect to 135BC’s resale of electricity, supplied by British Columbia Hydro and Power Authority (BC Hydro) to the NOS Substation located at 8546 Willow Cale Road in Prince George, British Columbia (NOS Substation), to purchasers whose facilities are connected to the NOS Substation (Application);
B. 135BC is a wholly owned subsidiary of 437218 B.C. Ltd. (437BC), both of which are companies within the Dakus Group of companies;
C. On August 27, 2015, by Order G-141-15, the BCUC, with advance approval from the Lieutenant Governor in Council, ordered that Canfor Forest Products Ltd. (Canfor) was exempt from the requirements of Part 3 of the UCA except for sections 25, 38, 42, and 43 for its NOS Substation distribution facilities used to supply electric service to its customers. The order also exempted both Canfor and any person that receives energy from Canfor’s NOS Substation distribution, from section 71 of the UCA provided the person is not re-selling energy to others;
D. In the Application, 135BC states that the NOS Substation is currently owned by Canfor and that Canfor, 135BC, and 437BC have entered into a Purchase Agreement, dated June 11, 2022, with respect to the purchase and sale of, among other things, the NOS Substation by Canfor to 135BC;
E. 135BC states that 135BC and three other parties with industrial facilities in the vicinity of the NOS Substation receive electricity service via the NOS Substation and distribution lines, and that 135BC will continue to provide such service upon completion of the purchase of the NOS Substation;
F. In accordance with section 1 of the UCA, 135BC will fall within the definition of “public utility” by reselling energy to others; and
G. The BCUC has determined that the establishment of a written comment process is warranted for the review of the Application.
NOW THEREFORE the BCUC orders as follows:
1. A public written comment process is established in accordance with the regulatory timetable as set out in Appendix A to this order;
2. 135BC is directed, as soon as reasonably possible but no later than Tuesday, November 15, 2022, to provide notice of the Application and a copy of this order, electronically where possible, to all impacted and potentially impacted parties, including BC Hydro, Canfor, all customers receiving service from the NOS Substation, and all potentially affected Indigenous communities in the area;
3. 135BC is directed to post this order in a clearly visible location on the homepage of its website and on all its social media platforms, if any, on or before Tuesday, November 15, 2022;
4. 135BC is directed to request that Canfor post this order in a clearly visible location on the News and Press Releases page of its website and on all its social media platforms, if any, on or before Tuesday, November 15, 2022;
5. 135BC is directed to provide to the BCUC, by Wednesday, November 16, 2022, a list of those who received notice of the Application, as directed in Directive 2 of this order; and
6. Parties wishing to provide comments on the Application are invited to submit letters of comment, by the date established in the regulatory timetable. Letters of comment must be in the Letter of Comment Form available on the BCUC’s website at: http://www.bcuc.com/forms/letter-of-comment.aspx, and submitted by email to commission.secretary@bcuc.com or by mail to the British Columbia Utilities Commission, Suite 410, 900 Howe Street, Vancouver, BC, V6Z 2N3.
DATED at the City of Vancouver, in the Province of British Columbia, this 8th day of November 2022.
BY ORDER
Original signed by:
B. A. Magnan
Commissioner
Attachment
1358037 B.C. Ltd.
Application for Exemption Under
Section 88(3) of the Utilities Commission Act
REGULATORY TIMETABLE
Action |
Date (2022) |
135BC to provide notice of Application |
Tuesday, November 15 |
135BC to provide confirmation of compliance with notice requirements |
Wednesday, November 16 |
BCUC Information Request (IR) No. 1 to 135BC |
Wednesday, November 30 |
135BC to provide responses to BCUC IR No. 1 |
Wednesday, December 7 |
Deadline to submit Letters of Comment |
Wednesday, December 14 |
Further process |
To be determined |