ORDER NUMBER

G-8-23

 

IN THE MATTER OF

the Utilities Commission Act, RSBC 1996, Chapter 473

 

and

 

British Columbia Hydro and Power Authority

Application for a Certificate of Public Convenience and Necessity

for the Lower Mainland Reactive Power Reinforcement Project

 

BEFORE:

A. K. Fung, KC, Panel Chair

A. C. Dennier, Commissioner

A. Pape-Salmon, Commissioner

 

on January 16, 2023

 

ORDER

 

WHEREAS:

 

A.      On November 22, 2022, British Columbia Hydro and Power Authority (BC Hydro) filed an application with the British Columbia Utilities Commission (BCUC) pursuant to section 45 and 46 of the Utilities Commission Act (UCA) seeking a Certificate of Public Convenience and Necessity (CPCN) for the Lower Mainland Reactive Power Reinforcement Project (Application);

B.      In the Application, BC Hydro proposes to install reactive power compensation equipment at the Meridian, Ingledow, McLellan and Clayburn substations and stop using the Burrard Synchronous Condenser Station to manage reactive power on BC Hydro’s transmission system; 

C.      By Order G-363-22, dated December 15, 2022, the BCUC established a regulatory timetable for a review of the Application; and

D.      The BCUC has commenced review of the Application and determines that a further regulatory timetable is warranted.

 

NOW THEREFORE the BCUC orders that the regulatory timetable is amended as set out in Appendix A to this order.

 

 

 

 

 

DATED at the City of Vancouver, in the Province of British Columbia, this          16th           day of January 2023.

 

BY ORDER

 

Original signed by:

 

A. K. Fung, KC

Commissioner

 

 


British Columbia Hydro and Power Authority

Application for a Certificate of Public Convenience and Necessity

for the Lower Mainland Reactive Power Reinforcement Project

 

REGULATORY TIMETABLE

 

 

Action

Date (2023)

Intervener Registration Deadline

Thursday, January 19

BC Hydro Workshop*

Monday, February 27

BCUC Information Request (IR) No. 1 to BC Hydro

Monday, March 20

Intervener IR No. 1 to BC Hydro

Monday April 3

BC Hydro Responses to BCUC and Intervener IR No.1

Monday, April 24

Further Process

To be Determined

 

*To be held in-person, commencing at 9 am. Active participation in the workshop, which will be transcribed, will be limited to BC Hydro, the BCUC and registered interveners; however, any party may follow the live broadcast. Further details regarding the workshop will be issued in due course.

 